The Heart Of Europe construction progress
The Heart Of Europe in The World was registered to complete in September 2022 and is still under construction. At the last site inspection, in May 2026, it was 82% built. The developer is T H O E Real Estate Development.
82%
Built, at the site inspection of 12 May 2026
50 months past its registered completion date
- Registered completion date
- September 2022
- Finish at recent pace
- April 2033
- Construction started
- April 2015
- First registered
- August 2015
- Developer
- T H O E Real Estate Development
- Community
- The World
- Units
- 10
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- ذا هيرت أوف يورب
- Project number
- 1671
- Site inspections
- 18
Schedule
The Heart Of Europe was registered to complete in September 2022, 50 months ago, and is still under construction. Over the last year of inspections it has added about 0.2 points a month. Kept at that rate, the site would reach 100% around April 2033.
Site inspections
12 May 2026
82%+2.2 pts
29 June 2025
80%+1.1 pts
4 July 2022
79%+0.1 pts
10 January 2022
79%+0.1 pts
11 August 2021
79%+0.6 pts
17 March 2021
78%+1.1 pts
29 June 2020
77%+2.9 pts
9 March 2020
74%+2.1 pts
27 August 2019
72%+2.0 pts
21 May 2019
70%+3.0 pts
Context
The World has 7 projects under construction, 66% built on average.
T H O E Real Estate Development has 4 projects under construction in Dubai; 3 have passed their registered completion date.
Own a unit in The Heart Of Europe?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the The Heart Of Europe handover date?
- The registered completion date was September 2022, and the register still lists The Heart Of Europe as under construction. At the pace of its recent inspections the site would reach 100% around April 2033. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on The Heart Of Europe?
- The Heart Of Europe was 82% built at the site inspection on 12 May 2026. The site has been inspected 18 times since June 2016. The Land Department took 193 site photos at its inspections.
- Is The Heart Of Europe delayed?
- Yes. Its registered completion date of September 2022 has passed and the project is still listed as under construction.
- Who is building The Heart Of Europe?
- The registered developer is T H O E Real Estate Development. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for The Heart Of Europe?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Sea Horse VillaAlso by T H O E Real Estate Development. 50%.
- The Heart Of Europe 1Also by T H O E Real Estate Development. 86%, Due September 2022, passed.
- The Heart Of Europe 2Also by T H O E Real Estate Development. 93%, Due April 2025, passed.
- Zaya Zuha IslandNearby in The World. 81%, Due June 2025, passed.
- Marbella Resort Hotel, A Vignette Collection World Islands DubaiNearby in The World. 47%.
- Amali IslandNearby in The World. 19%, Due March 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)




.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)

.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)