The Heart Of Europe 2 construction progress
The Heart Of Europe 2 in The World is 93% built at the Land Department inspection of February 2026. Developer T H O E Real Estate Development. Completion registered for April 2025.
93%
Built, at the Land Department site inspection of 26 February 2026
17 months past its registered completion date
- Completion date (Land Department)
- April 2025
- Finish at recent pace
- February 2031
- Construction started
- December 2015
- Registered with the Land Department
- May 2017
- Developer
- T H O E Real Estate Development
- Community
- The World
- Units
- 1,383
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- ذا هارت أوف يوروب 2
- Land Department project number
- 1842
- Land Department site inspections
- 23
Schedule
The Heart Of Europe 2 was registered to complete in April 2025, 17 months ago, and is still under construction. Over the last year of inspections it has added about 0.1 points a month. Kept at that rate, the site would reach 100% around February 2031.
Site inspections
26 February 2026
93%+0.4 pts
19 November 2025
93%+3.0 pts
29 October 2024
90%+1.8 pts
21 May 2024
88%+3.1 pts
19 October 2023
85%+1.0 pts
15 August 2023
84%+1.4 pts
3 April 2023
83%+0.5 pts
23 January 2023
82%+0.2 pts
4 July 2022
82%+0.7 pts
29 November 2021
81%+1.3 pts
Context
The World has 7 projects under construction, 65% built on average.
T H O E Real Estate Development has 4 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in The Heart Of Europe 2?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will The Heart Of Europe 2 be completed?
- The completion date registered with the Dubai Land Department is April 2025. At the pace of its recent inspections the site would reach 100% around February 2031. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of The Heart Of Europe 2 is built?
- 93%, measured at the Land Department site inspection on 26 February 2026. The Land Department engineers have inspected the site 23 times since August 2017.
- Is The Heart Of Europe 2 delayed?
- Yes. Its registered completion date of April 2025 has passed and the Land Department still lists it as under construction.
- Who is building The Heart Of Europe 2?
- The registered developer is T H O E Real Estate Development. It has 3 other projects under construction in Dubai.
- Which bank holds the escrow account for The Heart Of Europe 2?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Sea Horse VillaAlso by T H O E Real Estate Development. 50%.
- The Heart Of EuropeAlso by T H O E Real Estate Development. 82%.
- The Heart Of Europe 1Also by T H O E Real Estate Development. 86%.
- Zaya Zuha IslandNearby in The World. 81%, Due June 2025, passed.
- Marbella Resort Hotel, A Vignette Collection World Islands DubaiNearby in The World. 47%.
- Amali IslandNearby in The World. 16%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.















.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
%2520(9).jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)