The Heart Of Europe 2 construction progress

The Heart Of Europe 2 in The World was registered to complete in April 2025 and is still under construction. At the last site inspection, in February 2026, it was 93% built. The developer is T H O E Real Estate Development.

93%

Built, at the site inspection of 26 February 2026

19 months past its registered completion date

Registered completion date
April 2025
Finish at recent pace
February 2031
Construction started
December 2015
First registered
May 2017
Community
The World
Units
1,383
Escrow bank
Dubai Islamic Bank
Name in Arabic
ذا هارت أوف يوروب 2
Project number
1842
Site inspections
23

Schedule

The Heart Of Europe 2 was registered to complete in April 2025, 19 months ago, and is still under construction. Over the last year of inspections it has added about 0.1 points a month. Kept at that rate, the site would reach 100% around February 2031.

0%25%50%75%100%201620182020202220242026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

26 February 2026

93%+0.4 pts

  • The Heart Of Europe 2 construction site, inspection photo 1, 26 February 2026
  • The Heart Of Europe 2 construction site, inspection photo 2, 26 February 2026
  • The Heart Of Europe 2 construction site, inspection photo 3, 26 February 2026
  • The Heart Of Europe 2 construction site, inspection photo 4, 26 February 2026

19 November 2025

93%+3.0 pts

  • The Heart Of Europe 2 construction site, inspection photo 1, 19 November 2025
  • The Heart Of Europe 2 construction site, inspection photo 2, 19 November 2025
  • The Heart Of Europe 2 construction site, inspection photo 3, 19 November 2025
  • The Heart Of Europe 2 construction site, inspection photo 4, 19 November 2025

29 October 2024

90%+1.8 pts

  • The Heart Of Europe 2 construction site, inspection photo 1, 29 October 2024
  • The Heart Of Europe 2 construction site, inspection photo 2, 29 October 2024
  • The Heart Of Europe 2 construction site, inspection photo 3, 29 October 2024
  • The Heart Of Europe 2 construction site, inspection photo 4, 29 October 2024

21 May 2024

88%+3.1 pts

  • The Heart Of Europe 2 construction site, inspection photo 1, 21 May 2024
  • The Heart Of Europe 2 construction site, inspection photo 2, 21 May 2024
  • The Heart Of Europe 2 construction site, inspection photo 3, 21 May 2024
  • The Heart Of Europe 2 construction site, inspection photo 4, 21 May 2024

19 October 2023

85%+1.0 pts

  • The Heart Of Europe 2 construction site, inspection photo 1, 19 October 2023
  • The Heart Of Europe 2 construction site, inspection photo 2, 19 October 2023
  • The Heart Of Europe 2 construction site, inspection photo 3, 19 October 2023
  • The Heart Of Europe 2 construction site, inspection photo 4, 19 October 2023

15 August 2023

84%+1.4 pts

  • The Heart Of Europe 2 construction site, inspection photo 1, 15 August 2023
  • The Heart Of Europe 2 construction site, inspection photo 2, 15 August 2023
  • The Heart Of Europe 2 construction site, inspection photo 3, 15 August 2023
  • The Heart Of Europe 2 construction site, inspection photo 4, 15 August 2023

3 April 2023

83%+0.5 pts

  • The Heart Of Europe 2 construction site, inspection photo 1, 3 April 2023
  • The Heart Of Europe 2 construction site, inspection photo 2, 3 April 2023
  • The Heart Of Europe 2 construction site, inspection photo 3, 3 April 2023
  • The Heart Of Europe 2 construction site, inspection photo 4, 3 April 2023

23 January 2023

82%+0.2 pts

  • The Heart Of Europe 2 construction site, inspection photo 1, 23 January 2023
  • The Heart Of Europe 2 construction site, inspection photo 2, 23 January 2023
  • The Heart Of Europe 2 construction site, inspection photo 3, 23 January 2023
  • The Heart Of Europe 2 construction site, inspection photo 4, 23 January 2023

4 July 2022

82%+0.7 pts

  • The Heart Of Europe 2 construction site, inspection photo 1, 4 July 2022
  • The Heart Of Europe 2 construction site, inspection photo 2, 4 July 2022
  • The Heart Of Europe 2 construction site, inspection photo 3, 4 July 2022
  • The Heart Of Europe 2 construction site, inspection photo 4, 4 July 2022

29 November 2021

81%+1.3 pts

  • The Heart Of Europe 2 construction site, inspection photo 1, 29 November 2021
  • The Heart Of Europe 2 construction site, inspection photo 2, 29 November 2021
  • The Heart Of Europe 2 construction site, inspection photo 3, 29 November 2021
  • The Heart Of Europe 2 construction site, inspection photo 4, 29 November 2021

All 263 site photos, by inspection date

Context

The World has 7 projects under construction, 66% built on average.

T H O E Real Estate Development has 4 projects under construction in Dubai; 3 have passed their registered completion date.

Own a unit in The Heart Of Europe 2?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Heart Of Europe 2 handover date?
The registered completion date was April 2025, and the register still lists The Heart Of Europe 2 as under construction. At the pace of its recent inspections the site would reach 100% around February 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Heart Of Europe 2?
The Heart Of Europe 2 was 93% built at the site inspection on 26 February 2026. The site has been inspected 23 times since August 2017. The Land Department took 263 site photos at its inspections.
Is The Heart Of Europe 2 delayed?
Yes. Its registered completion date of April 2025 has passed and the project is still listed as under construction.
Who is building The Heart Of Europe 2?
The registered developer is T H O E Real Estate Development. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for The Heart Of Europe 2?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.