The Heart Of Europe 1 construction photos
171 photos from 16 site inspections, newest first. The percentage is how much of The Heart Of Europe 1 was built on the day of each visit.
12 May 202686% built
29 June 202584% built
4 July 202278% built
10 January 202278% built
11 August 202178% built
17 March 202173% built
9 March 202072% built
27 August 201966% built
21 May 201960% built
24 February 201952% built
12 December 201845% built
19 September 201841% built
5 July 201833% built
26 March 201823% built
23 January 201817% built
6 August 201711% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)



.jpeg&w=3840&q=75)












.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)