Amali Island construction progress

The registered completion date for Amali Island in The World is March 2027. At the last site inspection, in October 2026, it was 19% built. The developer is Amali Properties.

19%

Built, at the site inspection of 27 October 2026

Running behind its date

Registered completion date
March 2027
Finish at recent pace
August 2035
Construction started
July 2024
First registered
May 2024
Developer
Amali Properties
Community
The World
Units
24
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
جزيرة أمالي
Project number
3038
Site inspections
7

Schedule

Between January 2026 and October 2026 the site added about 0.8 points a month. At that rate it would finish around August 2035, more than three months after its registered date of March 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

27 October 2026

19%+2.3 pts

  • Amali Island construction site, inspection photo 1, 27 October 2026
  • Amali Island construction site, inspection photo 2, 27 October 2026
  • Amali Island construction site, inspection photo 3, 27 October 2026
  • Amali Island construction site, inspection photo 4, 27 October 2026

11 June 2026

16%+4.7 pts

  • Amali Island construction site, inspection photo 1, 11 June 2026
  • Amali Island construction site, inspection photo 2, 11 June 2026
  • Amali Island construction site, inspection photo 3, 11 June 2026
  • Amali Island construction site, inspection photo 4, 11 June 2026

21 January 2026

12%+4.7 pts

  • Amali Island construction site, inspection photo 1, 21 January 2026
  • Amali Island construction site, inspection photo 2, 21 January 2026
  • Amali Island construction site, inspection photo 3, 21 January 2026

2 September 2025

7.0%+1.2 pts

  • Amali Island construction site, inspection photo 1, 2 September 2025
  • Amali Island construction site, inspection photo 2, 2 September 2025
  • Amali Island construction site, inspection photo 3, 2 September 2025

5 May 2025

5.7%+4.5 pts

  • Amali Island construction site, inspection photo 1, 5 May 2025
  • Amali Island construction site, inspection photo 2, 5 May 2025
  • Amali Island construction site, inspection photo 3, 5 May 2025
  • Amali Island construction site, inspection photo 4, 5 May 2025

20 December 2024

1.2%+1.2 pts

  • Amali Island construction site, inspection photo 1, 20 December 2024
  • Amali Island construction site, inspection photo 2, 20 December 2024
  • Amali Island construction site, inspection photo 3, 20 December 2024

25 April 2024

0%

  • Amali Island construction site, inspection photo 1, 25 April 2024
  • Amali Island construction site, inspection photo 2, 25 April 2024
  • Amali Island construction site, inspection photo 3, 25 April 2024

All 30 site photos, by inspection date

Context

The World has 7 projects under construction, 66% built on average.

Own a unit in Amali Island?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Amali Island handover date?
The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2035. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Amali Island?
Amali Island was 19% built at the site inspection on 27 October 2026. The site has been inspected 7 times since April 2024. The Land Department took 30 site photos at its inspections.
Is Amali Island delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Amali Island?
The registered developer is Amali Properties.
Which bank holds the escrow account for Amali Island?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.