Amali Island construction progress
The registered completion date for Amali Island in The World is March 2027. At the last site inspection, in October 2026, it was 19% built. The developer is Amali Properties.
19%
Built, at the site inspection of 27 October 2026
Running behind its date
- Registered completion date
- March 2027
- Finish at recent pace
- August 2035
- Construction started
- July 2024
- First registered
- May 2024
- Developer
- Amali Properties
- Community
- The World
- Units
- 24
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- جزيرة أمالي
- Project number
- 3038
- Site inspections
- 7
Schedule
Between January 2026 and October 2026 the site added about 0.8 points a month. At that rate it would finish around August 2035, more than three months after its registered date of March 2027.
Site inspections
27 October 2026
19%+2.3 pts
11 June 2026
16%+4.7 pts
21 January 2026
12%+4.7 pts
2 September 2025
7.0%+1.2 pts
5 May 2025
5.7%+4.5 pts
20 December 2024
1.2%+1.2 pts
25 April 2024
0%
Context
The World has 7 projects under construction, 66% built on average.
Own a unit in Amali Island?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Amali Island handover date?
- The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2035. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Amali Island?
- Amali Island was 19% built at the site inspection on 27 October 2026. The site has been inspected 7 times since April 2024. The Land Department took 30 site photos at its inspections.
- Is Amali Island delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
- Who is building Amali Island?
- The registered developer is Amali Properties.
- Which bank holds the escrow account for Amali Island?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Sea Horse VillaNearby in The World. 50%.
- The Heart Of EuropeNearby in The World. 82%, Due September 2022, passed.
- The Heart Of Europe 1Nearby in The World. 86%, Due September 2022, passed.
- The Heart Of Europe 2Nearby in The World. 93%, Due April 2025, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.




.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)