Zaya Zuha Island construction progress
Zaya Zuha Island in The World is 81% built at the Land Department inspection of July 2025. Developer Zaya Zuha Island For Real Estate Development. Completion registered for June 2025.
81%
Built, at the Land Department site inspection of 31 July 2025
15 months past its registered completion date
- Completion date (Land Department)
- June 2025
- Finish at recent pace
- December 2025
- Construction started
- March 2023
- Registered with the Land Department
- March 2023
- Developer
- Zaya Zuha Island For Real Estate Development
- Community
- The World
- Units
- 28
- Escrow bank
- Commercial Bank of Dubai
- Name in Arabic
- جزيرة زايا زوها
- Land Department project number
- 2588
- Land Department site inspections
- 7
Schedule
Zaya Zuha Island was registered to complete in June 2025, 15 months ago, and is still under construction. Over the last year of inspections it has added about 4.5 points a month. Kept at that rate, the site would reach 100% around December 2025.
Site inspections
31 July 2025
81%+13 pts
24 March 2025
68%+24 pts
28 October 2024
43%+13 pts
22 August 2024
30%+12 pts
20 March 2024
18%+14 pts
6 October 2023
3.8%+0.3 pts
2 March 2023
3.5%
Context
The World has 7 projects under construction, 65% built on average.
Own a unit in Zaya Zuha Island?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Zaya Zuha Island be completed?
- The completion date registered with the Dubai Land Department is June 2025. At the pace of its recent inspections the site would reach 100% around December 2025. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Zaya Zuha Island is built?
- 81%, measured at the Land Department site inspection on 31 July 2025. The Land Department engineers have inspected the site 7 times since March 2023.
- Is Zaya Zuha Island delayed?
- Yes. Its registered completion date of June 2025 has passed and the Land Department still lists it as under construction.
- Who is building Zaya Zuha Island?
- The registered developer is Zaya Zuha Island For Real Estate Development.
- Which bank holds the escrow account for Zaya Zuha Island?
- Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Sea Horse VillaNearby in The World. 50%.
- The Heart Of EuropeNearby in The World. 82%.
- The Heart Of Europe 1Nearby in The World. 86%.
- The Heart Of Europe 2Nearby in The World. 93%, Due April 2025, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.








.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)









.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)