Zaya Zuha Island construction progress

Zaya Zuha Island in The World is 81% built at the Land Department inspection of July 2025. Developer Zaya Zuha Island For Real Estate Development. Completion registered for June 2025.

81%

Built, at the Land Department site inspection of 31 July 2025

15 months past its registered completion date

Completion date (Land Department)
June 2025
Finish at recent pace
December 2025
Construction started
March 2023
Registered with the Land Department
March 2023
Developer
Zaya Zuha Island For Real Estate Development
Community
The World
Units
28
Escrow bank
Commercial Bank of Dubai
Name in Arabic
جزيرة زايا زوها
Land Department project number
2588
Land Department site inspections
7

Schedule

Zaya Zuha Island was registered to complete in June 2025, 15 months ago, and is still under construction. Over the last year of inspections it has added about 4.5 points a month. Kept at that rate, the site would reach 100% around December 2025.

0%25%50%75%100%20242025
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

31 July 2025

81%+13 pts

  • Zaya Zuha Island construction site, Land Department inspection photo 1, 31 July 2025
  • Zaya Zuha Island construction site, Land Department inspection photo 2, 31 July 2025
  • Zaya Zuha Island construction site, Land Department inspection photo 3, 31 July 2025
  • Zaya Zuha Island construction site, Land Department inspection photo 4, 31 July 2025

24 March 2025

68%+24 pts

  • Zaya Zuha Island construction site, Land Department inspection photo 1, 24 March 2025
  • Zaya Zuha Island construction site, Land Department inspection photo 2, 24 March 2025
  • Zaya Zuha Island construction site, Land Department inspection photo 3, 24 March 2025
  • Zaya Zuha Island construction site, Land Department inspection photo 4, 24 March 2025

28 October 2024

43%+13 pts

  • Zaya Zuha Island construction site, Land Department inspection photo 1, 28 October 2024
  • Zaya Zuha Island construction site, Land Department inspection photo 2, 28 October 2024
  • Zaya Zuha Island construction site, Land Department inspection photo 3, 28 October 2024
  • Zaya Zuha Island construction site, Land Department inspection photo 4, 28 October 2024

22 August 2024

30%+12 pts

  • Zaya Zuha Island construction site, Land Department inspection photo 1, 22 August 2024
  • Zaya Zuha Island construction site, Land Department inspection photo 2, 22 August 2024
  • Zaya Zuha Island construction site, Land Department inspection photo 3, 22 August 2024
  • Zaya Zuha Island construction site, Land Department inspection photo 4, 22 August 2024

20 March 2024

18%+14 pts

  • Zaya Zuha Island construction site, Land Department inspection photo 1, 20 March 2024
  • Zaya Zuha Island construction site, Land Department inspection photo 2, 20 March 2024
  • Zaya Zuha Island construction site, Land Department inspection photo 3, 20 March 2024
  • Zaya Zuha Island construction site, Land Department inspection photo 4, 20 March 2024

6 October 2023

3.8%+0.3 pts

  • Zaya Zuha Island construction site, Land Department inspection photo 1, 6 October 2023
  • Zaya Zuha Island construction site, Land Department inspection photo 2, 6 October 2023
  • Zaya Zuha Island construction site, Land Department inspection photo 3, 6 October 2023
  • Zaya Zuha Island construction site, Land Department inspection photo 4, 6 October 2023

2 March 2023

3.5%

  • Zaya Zuha Island construction site, Land Department inspection photo 1, 2 March 2023
  • Zaya Zuha Island construction site, Land Department inspection photo 2, 2 March 2023
  • Zaya Zuha Island construction site, Land Department inspection photo 3, 2 March 2023
  • Zaya Zuha Island construction site, Land Department inspection photo 4, 2 March 2023

All 45 site photos, by inspection date

Context

The World has 7 projects under construction, 65% built on average.

Own a unit in Zaya Zuha Island?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Zaya Zuha Island be completed?
The completion date registered with the Dubai Land Department is June 2025. At the pace of its recent inspections the site would reach 100% around December 2025. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Zaya Zuha Island is built?
81%, measured at the Land Department site inspection on 31 July 2025. The Land Department engineers have inspected the site 7 times since March 2023.
Is Zaya Zuha Island delayed?
Yes. Its registered completion date of June 2025 has passed and the Land Department still lists it as under construction.
Who is building Zaya Zuha Island?
The registered developer is Zaya Zuha Island For Real Estate Development.
Which bank holds the escrow account for Zaya Zuha Island?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.