Sobha Creek Vistas construction progress

The register lists Sobha Creek Vistas in Sobha Hartland as complete, with a registered completion date of January 2022. Its last site inspection on record was in January 2022. The developer is Sobha.

100%

Built, at the site inspection of 17 January 2022

Construction complete

Registered completion date
January 2022
Construction started
August 2018
First registered
May 2018
Developer
Sobha
Units
784
Escrow bank
Dubai Islamic Bank
Name in Arabic
شوبا كريك فيستاس
Project number
2066
Site inspections
10

Schedule

The register lists Sobha Creek Vistas as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2019202020212022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 January 2022

100%+7.0 pts

  • Sobha Creek Vistas construction site, inspection photo 1, 17 January 2022
  • Sobha Creek Vistas construction site, inspection photo 2, 17 January 2022
  • Sobha Creek Vistas construction site, inspection photo 3, 17 January 2022
  • Sobha Creek Vistas construction site, inspection photo 4, 17 January 2022

9 September 2021

93%+10.0 pts

  • Sobha Creek Vistas construction site, inspection photo 1, 9 September 2021
  • Sobha Creek Vistas construction site, inspection photo 2, 9 September 2021
  • Sobha Creek Vistas construction site, inspection photo 3, 9 September 2021
  • Sobha Creek Vistas construction site, inspection photo 4, 9 September 2021

5 April 2021

83%+8.0 pts

  • Sobha Creek Vistas construction site, inspection photo 1, 5 April 2021
  • Sobha Creek Vistas construction site, inspection photo 2, 5 April 2021
  • Sobha Creek Vistas construction site, inspection photo 3, 5 April 2021
  • Sobha Creek Vistas construction site, inspection photo 4, 5 April 2021

14 December 2020

75%+15 pts

  • Sobha Creek Vistas construction site, inspection photo 1, 14 December 2020
  • Sobha Creek Vistas construction site, inspection photo 2, 14 December 2020
  • Sobha Creek Vistas construction site, inspection photo 3, 14 December 2020
  • Sobha Creek Vistas construction site, inspection photo 4, 14 December 2020

22 July 2020

60%+24 pts

  • Sobha Creek Vistas construction site, inspection photo 1, 22 July 2020
  • Sobha Creek Vistas construction site, inspection photo 2, 22 July 2020
  • Sobha Creek Vistas construction site, inspection photo 3, 22 July 2020
  • Sobha Creek Vistas construction site, inspection photo 4, 22 July 2020

5 March 2020

36%+14 pts

  • Sobha Creek Vistas construction site, inspection photo 1, 5 March 2020
  • Sobha Creek Vistas construction site, inspection photo 2, 5 March 2020
  • Sobha Creek Vistas construction site, inspection photo 3, 5 March 2020
  • Sobha Creek Vistas construction site, inspection photo 4, 5 March 2020

29 October 2019

22%+4.8 pts

  • Sobha Creek Vistas construction site, inspection photo 1, 29 October 2019
  • Sobha Creek Vistas construction site, inspection photo 2, 29 October 2019
  • Sobha Creek Vistas construction site, inspection photo 3, 29 October 2019
  • Sobha Creek Vistas construction site, inspection photo 4, 29 October 2019

4 September 2019

17%+12 pts

  • Sobha Creek Vistas construction site, inspection photo 1, 4 September 2019
  • Sobha Creek Vistas construction site, inspection photo 2, 4 September 2019
  • Sobha Creek Vistas construction site, inspection photo 3, 4 September 2019
  • Sobha Creek Vistas construction site, inspection photo 4, 4 September 2019

5 May 2019

5.7%+4.3 pts

  • Sobha Creek Vistas construction site, inspection photo 1, 5 May 2019
  • Sobha Creek Vistas construction site, inspection photo 2, 5 May 2019
  • Sobha Creek Vistas construction site, inspection photo 3, 5 May 2019
  • Sobha Creek Vistas construction site, inspection photo 4, 5 May 2019

27 December 2018

1.4%

  • Sobha Creek Vistas construction site, inspection photo 1, 27 December 2018
  • Sobha Creek Vistas construction site, inspection photo 2, 27 December 2018
  • Sobha Creek Vistas construction site, inspection photo 3, 27 December 2018
  • Sobha Creek Vistas construction site, inspection photo 4, 27 December 2018

All 98 site photos, by inspection date

Context

Sobha Hartland has 3 projects under construction, 82% built on average.

Sobha has 27 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Sobha Creek Vistas?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Sobha Creek Vistas handover date?
Construction of Sobha Creek Vistas is recorded as complete, with a registered completion date of January 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Sobha Creek Vistas?
Sobha Creek Vistas was 100% built at the site inspection on 17 January 2022. The site has been inspected 10 times since December 2018. The Land Department took 98 site photos at its inspections.
Is Sobha Creek Vistas delayed?
The register lists construction as complete.
Who is building Sobha Creek Vistas?
The registered developer is Sobha. It has 27 other projects under construction in Dubai.
Which bank holds the escrow account for Sobha Creek Vistas?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.