Casa Serene construction progress

Casa Serene in Sobha Hartland is 74% built at the Land Department inspection of July 2026. Developer Altus Properties Development. Completion registered for December 2024.

74%

Built, at the Land Department site inspection of 13 July 2026

22 months past its registered completion date

Completion date (Land Department)
December 2024
Finish at recent pace
March 2028
Construction started
August 2023
Registered with the Land Department
May 2024
Developer
Altus Properties Development
Units
1
Escrow bank
First Abu Dhabi Bank
Name in Arabic
كازا سيرين
Land Department project number
2878
Land Department site inspections
3

Schedule

Casa Serene was registered to complete in December 2024, 22 months ago, and is still under construction. Over the last year of inspections it has added about 1.3 points a month. Kept at that rate, the site would reach 100% around March 2028.

0%25%50%75%100%202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

13 July 2026

74%+22 pts

  • Casa Serene construction site, Land Department inspection photo 1, 13 July 2026
  • Casa Serene construction site, Land Department inspection photo 2, 13 July 2026
  • Casa Serene construction site, Land Department inspection photo 3, 13 July 2026
  • Casa Serene construction site, Land Department inspection photo 4, 13 July 2026

30 January 2025

52%+37 pts

  • Casa Serene construction site, Land Department inspection photo 1, 30 January 2025
  • Casa Serene construction site, Land Department inspection photo 2, 30 January 2025
  • Casa Serene construction site, Land Department inspection photo 3, 30 January 2025
  • Casa Serene construction site, Land Department inspection photo 4, 30 January 2025

28 February 2024

15%

  • Casa Serene construction site, Land Department inspection photo 1, 28 February 2024
  • Casa Serene construction site, Land Department inspection photo 2, 28 February 2024
  • Casa Serene construction site, Land Department inspection photo 3, 28 February 2024
  • Casa Serene construction site, Land Department inspection photo 4, 28 February 2024

All 21 site photos, by inspection date

Context

Sobha Hartland has 3 projects under construction, 82% built on average. Casa Serene is behind that average.

Own a unit in Casa Serene?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Casa Serene be completed?
The completion date registered with the Dubai Land Department is December 2024. At the pace of its recent inspections the site would reach 100% around March 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Casa Serene is built?
74%, measured at the Land Department site inspection on 13 July 2026. The Land Department engineers have inspected the site 3 times since February 2024.
Is Casa Serene delayed?
Yes. Its registered completion date of December 2024 has passed and the Land Department still lists it as under construction.
Who is building Casa Serene?
The registered developer is Altus Properties Development.
Which bank holds the escrow account for Casa Serene?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.