Casa Serene construction progress

Casa Serene in Sobha Hartland was registered to complete in December 2024 and is still under construction. At the last site inspection, in July 2026, it was 74% built. The developer is Altus Properties Development.

74%

Built, at the site inspection of 13 July 2026

24 months past its registered completion date

Registered completion date
December 2024
Finish at recent pace
March 2028
Construction started
August 2023
First registered
May 2024
Developer
Altus Properties Development
Units
1
Escrow bank
First Abu Dhabi Bank
Name in Arabic
كازا سيرين
Project number
2878
Site inspections
3

Schedule

Casa Serene was registered to complete in December 2024, 24 months ago, and is still under construction. Over the last year of inspections it has added about 1.3 points a month. Kept at that rate, the site would reach 100% around March 2028.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

13 July 2026

74%+22 pts

  • Casa Serene construction site, inspection photo 1, 13 July 2026
  • Casa Serene construction site, inspection photo 2, 13 July 2026
  • Casa Serene construction site, inspection photo 3, 13 July 2026
  • Casa Serene construction site, inspection photo 4, 13 July 2026

30 January 2025

52%+37 pts

  • Casa Serene construction site, inspection photo 1, 30 January 2025
  • Casa Serene construction site, inspection photo 2, 30 January 2025
  • Casa Serene construction site, inspection photo 3, 30 January 2025
  • Casa Serene construction site, inspection photo 4, 30 January 2025

28 February 2024

15%

  • Casa Serene construction site, inspection photo 1, 28 February 2024
  • Casa Serene construction site, inspection photo 2, 28 February 2024
  • Casa Serene construction site, inspection photo 3, 28 February 2024
  • Casa Serene construction site, inspection photo 4, 28 February 2024

All 21 site photos, by inspection date

Context

Sobha Hartland has 3 projects under construction, 82% built on average.

Own a unit in Casa Serene?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Casa Serene handover date?
The registered completion date was December 2024, and the register still lists Casa Serene as under construction. At the pace of its recent inspections the site would reach 100% around March 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Casa Serene?
Casa Serene was 74% built at the site inspection on 13 July 2026. The site has been inspected 3 times since February 2024. The Land Department took 21 site photos at its inspections.
Is Casa Serene delayed?
Yes. Its registered completion date of December 2024 has passed and the project is still listed as under construction.
Who is building Casa Serene?
The registered developer is Altus Properties Development.
Which bank holds the escrow account for Casa Serene?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.