Sobha Creek Vistas construction photos

98 photos from 10 site inspections, newest first. The percentage is how much of Sobha Creek Vistas was built on the day of each visit.

17 January 2022100% built

9 September 202193% built

5 April 202183% built

14 December 202075% built

22 July 202060% built

5 March 202036% built

29 October 201922% built

4 September 201917% built

5 May 20195.7% built

27 December 20181.4% built

Back to Sobha Creek Vistas construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.