Topaz Residences 2 construction progress

The register lists Topaz Residences 2 in Silicon Oasis as complete, with a registered completion date of January 2022. Its last site inspection on record was in April 2024. The developer is Gulf General Investments Co. (p.s.c).

100%

Built, at the site inspection of 21 April 2024

Construction complete

Registered completion date
January 2022
Construction started
August 2015
First registered
January 2016
Developer
Gulf General Investments Co. (p.s.c)
Community
Silicon Oasis
Units
202
Escrow bank
Dubai Islamic Bank
Name in Arabic
توباز ريزيدنسز 2
Project number
1708
Site inspections
6

Schedule

The register lists Topaz Residences 2 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20162018202020222024
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

21 April 2024

100%+26 pts

  • Topaz Residences 2 construction site, inspection photo 1, 21 April 2024
  • Topaz Residences 2 construction site, inspection photo 2, 21 April 2024
  • Topaz Residences 2 construction site, inspection photo 3, 21 April 2024
  • Topaz Residences 2 construction site, inspection photo 4, 21 April 2024

22 September 2023

74%+19 pts

  • Topaz Residences 2 construction site, inspection photo 1, 22 September 2023
  • Topaz Residences 2 construction site, inspection photo 2, 22 September 2023
  • Topaz Residences 2 construction site, inspection photo 3, 22 September 2023
  • Topaz Residences 2 construction site, inspection photo 4, 22 September 2023

31 October 2022

55%+3.5 pts

  • Topaz Residences 2 construction site, inspection photo 1, 31 October 2022
  • Topaz Residences 2 construction site, inspection photo 2, 31 October 2022
  • Topaz Residences 2 construction site, inspection photo 3, 31 October 2022
  • Topaz Residences 2 construction site, inspection photo 4, 31 October 2022

14 March 2018

52%+0.5 pts

  • Topaz Residences 2 construction site, inspection photo 1, 14 March 2018
  • Topaz Residences 2 construction site, inspection photo 2, 14 March 2018
  • Topaz Residences 2 construction site, inspection photo 3, 14 March 2018

11 October 2017

51%+1.0 pts

  • Topaz Residences 2 construction site, inspection photo 1, 11 October 2017
  • Topaz Residences 2 construction site, inspection photo 2, 11 October 2017
  • Topaz Residences 2 construction site, inspection photo 3, 11 October 2017
  • Topaz Residences 2 construction site, inspection photo 4, 11 October 2017

3 May 2017

50%

  • Topaz Residences 2 construction site, inspection photo 1, 3 May 2017
  • Topaz Residences 2 construction site, inspection photo 2, 3 May 2017
  • Topaz Residences 2 construction site, inspection photo 3, 3 May 2017
  • Topaz Residences 2 construction site, inspection photo 4, 3 May 2017

All 45 site photos, by inspection date

Context

Silicon Oasis has 10 projects under construction, 28% built on average.

Own a unit in Topaz Residences 2?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Topaz Residences 2 handover date?
Construction of Topaz Residences 2 is recorded as complete, with a registered completion date of January 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Topaz Residences 2?
Topaz Residences 2 was 100% built at the site inspection on 21 April 2024. The site has been inspected 6 times since May 2017. The Land Department took 45 site photos at its inspections.
Is Topaz Residences 2 delayed?
The register lists construction as complete.
Who is building Topaz Residences 2?
The registered developer is Gulf General Investments Co. (p.s.c).
Which bank holds the escrow account for Topaz Residences 2?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.