Topaz Residences 1 construction progress

The register lists Topaz Residences 1 in Silicon Oasis as complete, with a registered completion date of December 2018. Its last site inspection on record was in December 2018. The developer is Gulf General Investments Co. (p.s.c).

100%

Built, at the site inspection of 13 December 2018

Construction complete

Registered completion date
December 2018
Construction started
June 2014
First registered
February 2015
Developer
Gulf General Investments Co. (p.s.c)
Community
Silicon Oasis
Units
136
Escrow bank
Dubai Islamic Bank
Name in Arabic
توباز ريزيدينسيس 1
Project number
1635
Site inspections
7

Schedule

The register lists Topaz Residences 1 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2015201620172018
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

13 December 2018

100%+9.7 pts

  • Topaz Residences 1 construction site, inspection photo 1, 13 December 2018
  • Topaz Residences 1 construction site, inspection photo 2, 13 December 2018
  • Topaz Residences 1 construction site, inspection photo 3, 13 December 2018
  • Topaz Residences 1 construction site, inspection photo 4, 13 December 2018

14 March 2018

90%+10 pts

  • Topaz Residences 1 construction site, inspection photo 1, 14 March 2018
  • Topaz Residences 1 construction site, inspection photo 2, 14 March 2018
  • Topaz Residences 1 construction site, inspection photo 3, 14 March 2018
  • Topaz Residences 1 construction site, inspection photo 4, 14 March 2018

11 October 2017

80%+13 pts

  • Topaz Residences 1 construction site, inspection photo 1, 11 October 2017
  • Topaz Residences 1 construction site, inspection photo 2, 11 October 2017
  • Topaz Residences 1 construction site, inspection photo 3, 11 October 2017
  • Topaz Residences 1 construction site, inspection photo 4, 11 October 2017

23 February 2017

67%+12 pts

  • Topaz Residences 1 construction site, inspection photo 1, 23 February 2017
  • Topaz Residences 1 construction site, inspection photo 2, 23 February 2017
  • Topaz Residences 1 construction site, inspection photo 3, 23 February 2017
  • Topaz Residences 1 construction site, inspection photo 4, 23 February 2017

5 October 2016

55%+17 pts

  • Topaz Residences 1 construction site, inspection photo 1, 5 October 2016
  • Topaz Residences 1 construction site, inspection photo 2, 5 October 2016
  • Topaz Residences 1 construction site, inspection photo 3, 5 October 2016
  • Topaz Residences 1 construction site, inspection photo 4, 5 October 2016

10 February 2016

38%+14 pts

  • Topaz Residences 1 construction site, inspection photo 1, 10 February 2016
  • Topaz Residences 1 construction site, inspection photo 2, 10 February 2016
  • Topaz Residences 1 construction site, inspection photo 3, 10 February 2016
  • Topaz Residences 1 construction site, inspection photo 4, 10 February 2016

16 September 2015

24%

  • Topaz Residences 1 construction site, inspection photo 1, 16 September 2015
  • Topaz Residences 1 construction site, inspection photo 2, 16 September 2015
  • Topaz Residences 1 construction site, inspection photo 3, 16 September 2015

All 56 site photos, by inspection date

Context

Silicon Oasis has 10 projects under construction, 28% built on average.

Own a unit in Topaz Residences 1?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Topaz Residences 1 handover date?
Construction of Topaz Residences 1 is recorded as complete, with a registered completion date of December 2018. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Topaz Residences 1?
Topaz Residences 1 was 100% built at the site inspection on 13 December 2018. The site has been inspected 7 times since September 2015. The Land Department took 56 site photos at its inspections.
Is Topaz Residences 1 delayed?
The register lists construction as complete.
Who is building Topaz Residences 1?
The registered developer is Gulf General Investments Co. (p.s.c).
Which bank holds the escrow account for Topaz Residences 1?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.