Topaz Residences 1 construction photos
56 photos from 7 site inspections, newest first. The percentage is how much of Topaz Residences 1 was built on the day of each visit.
13 December 2018100% built
14 March 201890% built
11 October 201780% built
23 February 201767% built
5 October 201655% built
10 February 201638% built
16 September 201524% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.