Platinum Residence 1 construction progress

The register lists Platinum Residence 1 in Silicon Oasis as complete, with a registered completion date of October 2016. Its last site inspection on record was in December 2016. The developer is Gulf General Investments Co. (p.s.c).

100%

Built, at the site inspection of 5 December 2016

Construction complete

Registered completion date
October 2016
Construction started
September 2013
First registered
October 2014
Developer
Gulf General Investments Co. (p.s.c)
Community
Silicon Oasis
Units
120
Escrow bank
Dubai Islamic Bank
Name in Arabic
الإقامة البلاتينية 1
Project number
1589
Site inspections
3

Schedule

The register lists Platinum Residence 1 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201420152016
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

5 December 2016

100%+7.6 pts

  • Platinum Residence 1 construction site, inspection photo 1, 5 December 2016
  • Platinum Residence 1 construction site, inspection photo 2, 5 December 2016
  • Platinum Residence 1 construction site, inspection photo 3, 5 December 2016
  • Platinum Residence 1 construction site, inspection photo 4, 5 December 2016

7 September 2016

92%+22 pts

  • Platinum Residence 1 construction site, inspection photo 1, 7 September 2016
  • Platinum Residence 1 construction site, inspection photo 2, 7 September 2016
  • Platinum Residence 1 construction site, inspection photo 3, 7 September 2016
  • Platinum Residence 1 construction site, inspection photo 4, 7 September 2016

16 September 2015

71%

  • Platinum Residence 1 construction site, inspection photo 1, 16 September 2015

All 20 site photos, by inspection date

Context

Silicon Oasis has 10 projects under construction, 28% built on average.

Own a unit in Platinum Residence 1?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Platinum Residence 1 handover date?
Construction of Platinum Residence 1 is recorded as complete, with a registered completion date of October 2016. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Platinum Residence 1?
Platinum Residence 1 was 100% built at the site inspection on 5 December 2016. The site has been inspected 3 times since September 2015. The Land Department took 20 site photos at its inspections.
Is Platinum Residence 1 delayed?
The register lists construction as complete.
Who is building Platinum Residence 1?
The registered developer is Gulf General Investments Co. (p.s.c).
Which bank holds the escrow account for Platinum Residence 1?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.