Samana Hills South 3 construction progress

Samana Hills South 3 in Saih Shuaib 2 is 4.6% built at the Land Department inspection of June 2026. Developer Samana Signature Real Estate Developments. Completion registered for August 2028.

4.6%

Built, at the Land Department site inspection of 22 June 2026

Running behind its date

Completion date (Land Department)
August 2028
Finish at recent pace
August 2042
Construction started
September 2025
Registered with the Land Department
December 2025
Community
Saih Shuaib 2
Units
147
Escrow bank
Emirates NBD
Name in Arabic
سامانا هيلز جنوب 3
Land Department project number
4074
Land Department site inspections
2

Schedule

Between September 2025 and June 2026 the site added about 0.5 points a month. At that rate it would finish around August 2042, more than three months after the August 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

22 June 2026

4.6%+4.6 pts

  • Samana Hills South 3 construction site, Land Department inspection photo 1, 22 June 2026
  • Samana Hills South 3 construction site, Land Department inspection photo 2, 22 June 2026
  • Samana Hills South 3 construction site, Land Department inspection photo 3, 22 June 2026
  • Samana Hills South 3 construction site, Land Department inspection photo 4, 22 June 2026

11 September 2025

0%

  • Samana Hills South 3 construction site, Land Department inspection photo 1, 11 September 2025
  • Samana Hills South 3 construction site, Land Department inspection photo 2, 11 September 2025

All 6 site photos, by inspection date

Context

Saih Shuaib 2 has 10 projects under construction, 32% built on average.

Samana Signature Real Estate Developments has 12 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Samana Hills South 3?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Samana Hills South 3 be completed?
The completion date registered with the Dubai Land Department is August 2028. At the pace of its recent inspections the site would reach 100% around August 2042. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Samana Hills South 3 is built?
4.6%, measured at the Land Department site inspection on 22 June 2026. The Land Department engineers have inspected the site 2 times since September 2025.
Is Samana Hills South 3 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2028.
Who is building Samana Hills South 3?
The registered developer is Samana Signature Real Estate Developments. It has 11 other projects under construction in Dubai.
Which bank holds the escrow account for Samana Hills South 3?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.