Samana Hills South 3 construction progress
The registered completion date for Samana Hills South 3 in Saih Shuaib 2 is August 2028. At the last site inspection, in October 2026, it was 15% built. The developer is Samana Signature Real Estate Developments.
15%
Built, at the site inspection of 28 October 2026
Running behind its date
- Registered completion date
- August 2028
- Finish at recent pace
- September 2029
- Construction started
- September 2025
- First registered
- December 2025
- Community
- Saih Shuaib 2
- Units
- 147
- Escrow bank
- Emirates NBD
- Name in Arabic
- سامانا هيلز جنوب 3
- Project number
- 4074
- Site inspections
- 3
Schedule
Between June 2026 and October 2026 the site added about 2.5 points a month. At that rate it would finish around September 2029, more than three months after its registered date of August 2028.
Site inspections
28 October 2026
15%+10 pts
22 June 2026
4.6%+4.6 pts
11 September 2025
0%
Context
Saih Shuaib 2 has 6 projects under construction, 26% built on average.
Samana Signature Real Estate Developments has 12 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Samana Hills South 3?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Samana Hills South 3 handover date?
- The registered completion date is August 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Samana Hills South 3?
- Samana Hills South 3 was 15% built at the site inspection on 28 October 2026. The site has been inspected 3 times since September 2025. The Land Department took 10 site photos at its inspections.
- Is Samana Hills South 3 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2028.
- Who is building Samana Hills South 3?
- The registered developer is Samana Signature Real Estate Developments. It has 11 other projects under construction in Dubai.
- Which bank holds the escrow account for Samana Hills South 3?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Samana SkyrosAlso by Samana Signature Real Estate Developments. 71%, Due April 2026, passed.
- Samana Lake ViewsAlso by Samana Signature Real Estate Developments. 23%.
- Samana Lake Views 2Also by Samana Signature Real Estate Developments. 12%.
- Samana Barari LagoonsAlso by Samana Signature Real Estate Developments. 17%, Due March 2028.
- Sahara LivingsNearby in Saih Shuaib 2. 93%, Due June 2013, passed.
- Al Haseen Residence 3Nearby in Saih Shuaib 2. 10%, Due May 2027.
- Al Haseen Residence 4Nearby in Saih Shuaib 2. 12%, Due December 2026.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.