Al Haseen Residence construction progress
The register lists Al Haseen Residence in Saih Shuaib 2 as complete, with a registered completion date of April 2020. Its last site inspection on record was in May 2020. The developer is Dugasta Properties Development.
100%
Built, at the site inspection of 11 May 2020
Construction complete
- Registered completion date
- April 2020
- Construction started
- May 2017
- First registered
- March 2017
- Developer
- Dugasta Properties Development
- Community
- Saih Shuaib 2
- Units
- 138
- Escrow bank
- Mashreq Bank
- Name in Arabic
- الحسين رسيدانس
- Project number
- 1867
- Site inspections
- 10
Schedule
The register lists Al Haseen Residence as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.
Site inspections
11 May 2020
100%+4.4 pts
3 February 2020
96%+5.2 pts
19 September 2019
90%+10 pts
21 May 2019
80%+9.9 pts
31 January 2019
70%+14 pts
23 October 2018
56%+5.6 pts
18 July 2018
51%+15 pts
15 April 2018
36%+14 pts
9 January 2018
22%+7.9 pts
4 October 2017
14%
Context
Saih Shuaib 2 has 6 projects under construction, 26% built on average.
Dugasta Properties Development has 6 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Al Haseen Residence?
The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.
Notify me when it launchesQuestions
- When is the Al Haseen Residence handover date?
- Construction of Al Haseen Residence is recorded as complete, with a registered completion date of April 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
- What is the latest construction update on Al Haseen Residence?
- Al Haseen Residence was 100% built at the site inspection on 11 May 2020. The site has been inspected 10 times since October 2017. The Land Department took 101 site photos at its inspections.
- Is Al Haseen Residence delayed?
- The register lists construction as complete.
- Who is building Al Haseen Residence?
- The registered developer is Dugasta Properties Development. It has 6 other projects under construction in Dubai.
- Which bank holds the escrow account for Al Haseen Residence?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Terra TowerAlso by Dugasta Properties Development. 7.4%, Due April 2027.
- Moonsa Residences 2Also by Dugasta Properties Development. 1.0%, Due December 2026.
- Al Haseen Residence 3Also by Dugasta Properties Development. 10%, Due May 2027.
- Al Haseen Residence 4Also by Dugasta Properties Development. 12%, Due December 2026.
- Sahara LivingsNearby in Saih Shuaib 2. 93%, Due June 2013, passed.
- Samana Hills SouthNearby in Saih Shuaib 2. 12%, Due May 2028.
- Samana Hills South 2Nearby in Saih Shuaib 2. 12%, Due August 2028.
- Samana Hills South 3Nearby in Saih Shuaib 2. 15%, Due August 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.