101 photos from 10 site inspections, newest first. The percentage is how much of Al Haseen Residence was built on the day of each visit.

11 May 2020100% built

3 February 202096% built

19 September 201990% built

21 May 201980% built

31 January 201970% built

23 October 201856% built

18 July 201851% built

15 April 201836% built

9 January 201822% built

4 October 201714% built

Back to Al Haseen Residence construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.