Sobha One construction progress

No completion date is registered for Sobha One in Ras Al Khor Industrial First yet. At the last site inspection, in August 2026, it was 86% built. The developer is Sobha.

86%

Built, at the site inspection of 24 August 2026

Finish at recent pace
January 2027
Construction started
September 2023
First registered
February 2024
Developer
Sobha
Units
3,057
Escrow bank
Dubai Islamic Bank
Name in Arabic
شوبا ون
Project number
2948
Site inspections
9

Schedule

Since October 2025 Sobha One has added about 2.6 points a month. At that rate the site reaches 100% around January 2027. No completion date is on record to compare it with.

0%25%50%75%100%202420252026
Progress at each site inspection

Site inspections

24 August 2026

86%+6.1 pts

  • Sobha One construction site, inspection photo 1, 24 August 2026
  • Sobha One construction site, inspection photo 2, 24 August 2026
  • Sobha One construction site, inspection photo 3, 24 August 2026
  • Sobha One construction site, inspection photo 4, 24 August 2026

18 May 2026

80%+13 pts

  • Sobha One construction site, inspection photo 1, 18 May 2026
  • Sobha One construction site, inspection photo 2, 18 May 2026
  • Sobha One construction site, inspection photo 3, 18 May 2026
  • Sobha One construction site, inspection photo 4, 18 May 2026

9 February 2026

67%+8.7 pts

  • Sobha One construction site, inspection photo 1, 9 February 2026
  • Sobha One construction site, inspection photo 2, 9 February 2026
  • Sobha One construction site, inspection photo 3, 9 February 2026
  • Sobha One construction site, inspection photo 4, 9 February 2026

9 October 2025

58%+17 pts

  • Sobha One construction site, inspection photo 1, 9 October 2025
  • Sobha One construction site, inspection photo 2, 9 October 2025
  • Sobha One construction site, inspection photo 3, 9 October 2025
  • Sobha One construction site, inspection photo 4, 9 October 2025

19 May 2025

41%+8.4 pts

  • Sobha One construction site, inspection photo 1, 19 May 2025
  • Sobha One construction site, inspection photo 2, 19 May 2025
  • Sobha One construction site, inspection photo 3, 19 May 2025
  • Sobha One construction site, inspection photo 4, 19 May 2025

10 February 2025

33%+7.2 pts

  • Sobha One construction site, inspection photo 1, 10 February 2025
  • Sobha One construction site, inspection photo 2, 10 February 2025
  • Sobha One construction site, inspection photo 3, 10 February 2025
  • Sobha One construction site, inspection photo 4, 10 February 2025

4 November 2024

26%+8.2 pts

  • Sobha One construction site, inspection photo 1, 4 November 2024
  • Sobha One construction site, inspection photo 2, 4 November 2024
  • Sobha One construction site, inspection photo 3, 4 November 2024
  • Sobha One construction site, inspection photo 4, 4 November 2024

25 July 2024

17%+12 pts

  • Sobha One construction site, inspection photo 1, 25 July 2024
  • Sobha One construction site, inspection photo 2, 25 July 2024
  • Sobha One construction site, inspection photo 3, 25 July 2024
  • Sobha One construction site, inspection photo 4, 25 July 2024

13 February 2024

4.9%

  • Sobha One construction site, inspection photo 1, 13 February 2024
  • Sobha One construction site, inspection photo 2, 13 February 2024
  • Sobha One construction site, inspection photo 3, 13 February 2024
  • Sobha One construction site, inspection photo 4, 13 February 2024

All 81 site photos, by inspection date

Context

Ras Al Khor Industrial First has 3 projects under construction, 38% built on average.

Sobha has 27 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Sobha One?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Sobha One handover date?
No completion date is on record for Sobha One yet. Handover follows completion, so there is no date to give.
What is the latest construction update on Sobha One?
Sobha One was 86% built at the site inspection on 24 August 2026. The site has been inspected 9 times since February 2024. The Land Department took 81 site photos at its inspections.
Who is building Sobha One?
The registered developer is Sobha. It has 26 other projects under construction in Dubai.
Which bank holds the escrow account for Sobha One?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.