Amaal 8 construction progress
The registered completion date for Amaal 8 in Ras Al Khor Industrial First is December 2028. At the last site inspection, in October 2026, it was 11% built. The developer is Amaal Emirates.
11%
Built, at the site inspection of 28 October 2026
Running behind its date
- Registered completion date
- December 2028
- Finish at recent pace
- April 2036
- Construction started
- March 2024
- First registered
- September 2024
- Developer
- Amaal Emirates
- Community
- Ras Al Khor Industrial First
- Units
- 533
- Escrow bank
- Commercial Bank of Dubai
- Name in Arabic
- امال 8
- Project number
- 3004
- Site inspections
- 5
Schedule
Between March 2026 and October 2026 the site added about 0.8 points a month. At that rate it would finish around April 2036, more than three months after its registered date of December 2028.
Site inspections
28 October 2026
11%+4.2 pts
16 July 2026
7.0%+1.4 pts
24 March 2026
5.7%+4.1 pts
28 July 2025
1.6%+1.6 pts
5 April 2024
0%
Context
Ras Al Khor Industrial First has 3 projects under construction, 38% built on average.
Own a unit in Amaal 8?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Amaal 8 handover date?
- The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2036. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Amaal 8?
- Amaal 8 was 11% built at the site inspection on 28 October 2026. The site has been inspected 5 times since April 2024. The Land Department took 19 site photos at its inspections.
- Is Amaal 8 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
- Who is building Amaal 8?
- The registered developer is Amaal Emirates.
- Which bank holds the escrow account for Amaal 8?
- Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Sobha OneNearby in Ras Al Khor Industrial First. 86%.
- The Element At Sobha OneNearby in Ras Al Khor Industrial First. 17%, Due December 2029.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.







.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)