Amaal 8 construction progress

Amaal 8 in Ras Al Khor Industrial First is 7.0% built at the Land Department inspection of July 2026. Developer Amaal Emirates. Completion registered for December 2028.

7.0%

Built, at the Land Department site inspection of 16 July 2026

Running behind its date

Completion date (Land Department)
December 2028
Finish at recent pace
January 2043
Construction started
March 2024
Registered with the Land Department
September 2024
Developer
Amaal Emirates
Units
533
Escrow bank
Commercial Bank of Dubai
Name in Arabic
امال 8
Land Department project number
3004
Land Department site inspections
4

Schedule

Between July 2025 and July 2026 the site added about 0.5 points a month. At that rate it would finish around January 2043, more than three months after the December 2028 date registered with the Land Department.

0%25%50%75%100%2025202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

16 July 2026

7.0%+1.4 pts

  • Amaal 8 construction site, Land Department inspection photo 1, 16 July 2026
  • Amaal 8 construction site, Land Department inspection photo 2, 16 July 2026
  • Amaal 8 construction site, Land Department inspection photo 3, 16 July 2026
  • Amaal 8 construction site, Land Department inspection photo 4, 16 July 2026

24 March 2026

5.7%+4.1 pts

  • Amaal 8 construction site, Land Department inspection photo 1, 24 March 2026
  • Amaal 8 construction site, Land Department inspection photo 2, 24 March 2026
  • Amaal 8 construction site, Land Department inspection photo 3, 24 March 2026

28 July 2025

1.6%+1.6 pts

  • Amaal 8 construction site, Land Department inspection photo 1, 28 July 2025
  • Amaal 8 construction site, Land Department inspection photo 2, 28 July 2025

5 April 2024

0%

  • Amaal 8 construction site, Land Department inspection photo 1, 5 April 2024
  • Amaal 8 construction site, Land Department inspection photo 2, 5 April 2024

All 12 site photos, by inspection date

Context

Ras Al Khor Industrial First has 3 projects under construction, 35% built on average.

Own a unit in Amaal 8?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Amaal 8 be completed?
The completion date registered with the Dubai Land Department is December 2028. At the pace of its recent inspections the site would reach 100% around January 2043. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Amaal 8 is built?
7.0%, measured at the Land Department site inspection on 16 July 2026. The Land Department engineers have inspected the site 4 times since April 2024.
Is Amaal 8 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Amaal 8?
The registered developer is Amaal Emirates.
Which bank holds the escrow account for Amaal 8?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.