The Palm Tower construction progress

The register lists The Palm Tower in Palm Jumeirah as complete, with a registered completion date of November 2021. Its last site inspection on record was in March 2022. The developer is The Palm - Jumeirah Co.

100%

Built, at the site inspection of 14 March 2022

Construction complete

Registered completion date
November 2021
Construction started
February 2015
First registered
November 2014
Community
Palm Jumeirah
Units
450
Escrow bank
Mashreq Bank
Name in Arabic
ذا بالم تاور
Project number
1603
Site inspections
13

Schedule

The register lists The Palm Tower as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2016201820202022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 March 2022

100%+2.9 pts

  • The Palm Tower construction site, inspection photo 1, 14 March 2022
  • The Palm Tower construction site, inspection photo 2, 14 March 2022
  • The Palm Tower construction site, inspection photo 3, 14 March 2022
  • The Palm Tower construction site, inspection photo 4, 14 March 2022

24 October 2021

97%+6.9 pts

  • The Palm Tower construction site, inspection photo 1, 24 October 2021
  • The Palm Tower construction site, inspection photo 2, 24 October 2021
  • The Palm Tower construction site, inspection photo 3, 24 October 2021
  • The Palm Tower construction site, inspection photo 4, 24 October 2021

10 June 2021

90%+2.8 pts

  • The Palm Tower construction site, inspection photo 1, 10 June 2021
  • The Palm Tower construction site, inspection photo 2, 10 June 2021
  • The Palm Tower construction site, inspection photo 3, 10 June 2021
  • The Palm Tower construction site, inspection photo 4, 10 June 2021

1 April 2021

87%+2.3 pts

  • The Palm Tower construction site, inspection photo 1, 1 April 2021
  • The Palm Tower construction site, inspection photo 2, 1 April 2021
  • The Palm Tower construction site, inspection photo 3, 1 April 2021
  • The Palm Tower construction site, inspection photo 4, 1 April 2021

25 October 2020

85%+10 pts

  • The Palm Tower construction site, inspection photo 1, 25 October 2020
  • The Palm Tower construction site, inspection photo 2, 25 October 2020
  • The Palm Tower construction site, inspection photo 3, 25 October 2020
  • The Palm Tower construction site, inspection photo 4, 25 October 2020

27 August 2020

75%+17 pts

  • The Palm Tower construction site, inspection photo 1, 27 August 2020
  • The Palm Tower construction site, inspection photo 2, 27 August 2020
  • The Palm Tower construction site, inspection photo 3, 27 August 2020
  • The Palm Tower construction site, inspection photo 4, 27 August 2020

28 July 2019

58%+10 pts

  • The Palm Tower construction site, inspection photo 1, 28 July 2019
  • The Palm Tower construction site, inspection photo 2, 28 July 2019
  • The Palm Tower construction site, inspection photo 3, 28 July 2019
  • The Palm Tower construction site, inspection photo 4, 28 July 2019

23 January 2019

48%+7.6 pts

  • The Palm Tower construction site, inspection photo 1, 23 January 2019
  • The Palm Tower construction site, inspection photo 2, 23 January 2019
  • The Palm Tower construction site, inspection photo 3, 23 January 2019
  • The Palm Tower construction site, inspection photo 4, 23 January 2019

4 June 2018

40%+17 pts

  • The Palm Tower construction site, inspection photo 1, 4 June 2018
  • The Palm Tower construction site, inspection photo 2, 4 June 2018
  • The Palm Tower construction site, inspection photo 3, 4 June 2018
  • The Palm Tower construction site, inspection photo 4, 4 June 2018

20 March 2017

23%+2.4 pts

  • The Palm Tower construction site, inspection photo 1, 20 March 2017
  • The Palm Tower construction site, inspection photo 2, 20 March 2017
  • The Palm Tower construction site, inspection photo 3, 20 March 2017
  • The Palm Tower construction site, inspection photo 4, 20 March 2017

All 132 site photos, by inspection date

Context

Palm Jumeirah has 16 projects under construction, 45% built on average.

The Palm - Jumeirah Co has 4 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Palm Tower?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the The Palm Tower handover date?
Construction of The Palm Tower is recorded as complete, with a registered completion date of November 2021. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on The Palm Tower?
The Palm Tower was 100% built at the site inspection on 14 March 2022. The site has been inspected 13 times since October 2015. The Land Department took 132 site photos at its inspections.
Is The Palm Tower delayed?
The register lists construction as complete.
Who is building The Palm Tower?
The registered developer is The Palm - Jumeirah Co. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for The Palm Tower?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.