Skip to content

Como Residences construction progress

The registered completion date for Como Residences in Palm Jumeirah is March 2027. At the last site inspection, in October 2026, it was 25% built. The developer is The Palm - Jumeirah Co.

25%

Built, at the site inspection of 9 October 2026

Running behind its date

Registered completion date
March 2027
Finish at recent pace
January 2034
Construction started
September 2023
First registered
April 2023
Community
Palm Jumeirah
Units
81
Escrow bank
Commercial Bank of Dubai
Name in Arabic
كومو ريزيدنسز
Project number
2565
Site inspections
10

Schedule

Between November 2025 and October 2026 the site added about 0.9 points a month. At that rate it would finish around January 2034, more than three months after its registered date of March 2027.

0%25%50%75%100%2024202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

9 October 2026

25%+3.9 pts

  • Como Residences construction site, inspection photo 1, 9 October 2026
  • Como Residences construction site, inspection photo 2, 9 October 2026
  • Como Residences construction site, inspection photo 3, 9 October 2026
  • Como Residences construction site, inspection photo 4, 9 October 2026

6 July 2026

21%+2.6 pts

  • Como Residences construction site, inspection photo 1, 6 July 2026
  • Como Residences construction site, inspection photo 2, 6 July 2026
  • Como Residences construction site, inspection photo 3, 6 July 2026
  • Como Residences construction site, inspection photo 4, 6 July 2026

2 April 2026

18%+3.0 pts

  • Como Residences construction site, inspection photo 1, 2 April 2026
  • Como Residences construction site, inspection photo 2, 2 April 2026
  • Como Residences construction site, inspection photo 3, 2 April 2026
  • Como Residences construction site, inspection photo 4, 2 April 2026

10 November 2025

15%+4.5 pts

  • Como Residences construction site, inspection photo 1, 10 November 2025
  • Como Residences construction site, inspection photo 2, 10 November 2025
  • Como Residences construction site, inspection photo 3, 10 November 2025
  • Como Residences construction site, inspection photo 4, 10 November 2025

30 July 2025

11%+4.8 pts

  • Como Residences construction site, inspection photo 1, 30 July 2025
  • Como Residences construction site, inspection photo 2, 30 July 2025
  • Como Residences construction site, inspection photo 3, 30 July 2025
  • Como Residences construction site, inspection photo 4, 30 July 2025

1 May 2025

6.1%+1.8 pts

  • Como Residences construction site, inspection photo 1, 1 May 2025
  • Como Residences construction site, inspection photo 2, 1 May 2025
  • Como Residences construction site, inspection photo 3, 1 May 2025

28 January 2025

4.3%+1.6 pts

  • Como Residences construction site, inspection photo 1, 28 January 2025
  • Como Residences construction site, inspection photo 2, 28 January 2025
  • Como Residences construction site, inspection photo 3, 28 January 2025
  • Como Residences construction site, inspection photo 4, 28 January 2025

29 August 2024

2.7%+2.7 pts

  • Como Residences construction site, inspection photo 1, 29 August 2024
  • Como Residences construction site, inspection photo 2, 29 August 2024
  • Como Residences construction site, inspection photo 3, 29 August 2024

7 November 2023

0%+0.0 pts

  • Como Residences construction site, inspection photo 1, 7 November 2023
  • Como Residences construction site, inspection photo 2, 7 November 2023
  • Como Residences construction site, inspection photo 3, 7 November 2023
  • Como Residences construction site, inspection photo 4, 7 November 2023

22 February 2023

0%

  • Como Residences construction site, inspection photo 1, 22 February 2023
  • Como Residences construction site, inspection photo 2, 22 February 2023

All 57 site photos, by inspection date

Context

Palm Jumeirah has 16 projects under construction, 45% built on average.

The Palm - Jumeirah Co has 4 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Como Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Como Residences handover date?
The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2034. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Como Residences?
Como Residences was 25% built at the site inspection on 9 October 2026. The site has been inspected 10 times since February 2023. The Land Department took 57 site photos at its inspections.
Is Como Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Como Residences?
The registered developer is The Palm - Jumeirah Co. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for Como Residences?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.