One Crescent construction progress
One Crescent in Palm Jumeirah was registered to complete in March 2026 and is still under construction. At the last site inspection, in October 2026, it was 90% built. The developer is A H S Palm Development.
90%
Built, at the site inspection of 28 October 2026
9 months past its registered completion date
- Registered completion date
- March 2026
- Finish at recent pace
- January 2027
- Construction started
- May 2023
- First registered
- March 2023
- Developer
- A H S Palm Development
- Community
- Palm Jumeirah
- Units
- 25
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- وان كريسنت
- Project number
- 2567
- Site inspections
- 10
Schedule
One Crescent was registered to complete in March 2026, 9 months ago, and is still under construction. Over the last year of inspections it has added about 3.2 points a month. Kept at that rate, the site would reach 100% around January 2027.
Site inspections
28 October 2026
90%+10.0 pts
28 July 2026
80%+11 pts
17 April 2026
69%+7.3 pts
11 February 2026
61%+4.8 pts
15 December 2025
57%+22 pts
25 August 2025
34%+10 pts
7 May 2025
24%+14 pts
10 October 2024
10%+9.1 pts
10 October 2023
1.0%+1.0 pts
30 January 2023
0%
Context
Palm Jumeirah has 16 projects under construction, 45% built on average.
Own a unit in One Crescent?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the One Crescent handover date?
- The registered completion date was March 2026, and the register still lists One Crescent as under construction. At the pace of its recent inspections the site would reach 100% around January 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on One Crescent?
- One Crescent was 90% built at the site inspection on 28 October 2026. The site has been inspected 10 times since January 2023. The Land Department took 72 site photos at its inspections.
- Is One Crescent delayed?
- Yes. Its registered completion date of March 2026 has passed and the project is still listed as under construction.
- Who is building One Crescent?
- The registered developer is A H S Palm Development.
- Which bank holds the escrow account for One Crescent?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Palm Beach Towers -1Nearby in Palm Jumeirah. 83%, Due December 2026.
- Palm Beach Towers - 2Nearby in Palm Jumeirah. 82%, Due December 2026.
- Palm Beach Towers -3Nearby in Palm Jumeirah. 74%, Due December 2026.
- Orla By OmniyatNearby in Palm Jumeirah. 70%, Due December 2026.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.













.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)








.jpg&w=3840&q=75)
.jpg&w=3840&q=75)

.jpg&w=3840&q=75)