One Crescent construction progress

One Crescent in Palm Jumeirah was registered to complete in March 2026 and is still under construction. At the last site inspection, in October 2026, it was 90% built. The developer is A H S Palm Development.

90%

Built, at the site inspection of 28 October 2026

9 months past its registered completion date

Registered completion date
March 2026
Finish at recent pace
January 2027
Construction started
May 2023
First registered
March 2023
Developer
A H S Palm Development
Community
Palm Jumeirah
Units
25
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
وان كريسنت
Project number
2567
Site inspections
10

Schedule

One Crescent was registered to complete in March 2026, 9 months ago, and is still under construction. Over the last year of inspections it has added about 3.2 points a month. Kept at that rate, the site would reach 100% around January 2027.

0%25%50%75%100%202420252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

28 October 2026

90%+10.0 pts

  • One Crescent construction site, inspection photo 1, 28 October 2026
  • One Crescent construction site, inspection photo 2, 28 October 2026
  • One Crescent construction site, inspection photo 3, 28 October 2026
  • One Crescent construction site, inspection photo 4, 28 October 2026

28 July 2026

80%+11 pts

  • One Crescent construction site, inspection photo 1, 28 July 2026
  • One Crescent construction site, inspection photo 2, 28 July 2026
  • One Crescent construction site, inspection photo 3, 28 July 2026
  • One Crescent construction site, inspection photo 4, 28 July 2026

17 April 2026

69%+7.3 pts

  • One Crescent construction site, inspection photo 1, 17 April 2026
  • One Crescent construction site, inspection photo 2, 17 April 2026
  • One Crescent construction site, inspection photo 3, 17 April 2026
  • One Crescent construction site, inspection photo 4, 17 April 2026

11 February 2026

61%+4.8 pts

  • One Crescent construction site, inspection photo 1, 11 February 2026
  • One Crescent construction site, inspection photo 2, 11 February 2026
  • One Crescent construction site, inspection photo 3, 11 February 2026
  • One Crescent construction site, inspection photo 4, 11 February 2026

15 December 2025

57%+22 pts

  • One Crescent construction site, inspection photo 1, 15 December 2025
  • One Crescent construction site, inspection photo 2, 15 December 2025
  • One Crescent construction site, inspection photo 3, 15 December 2025
  • One Crescent construction site, inspection photo 4, 15 December 2025

25 August 2025

34%+10 pts

  • One Crescent construction site, inspection photo 1, 25 August 2025
  • One Crescent construction site, inspection photo 2, 25 August 2025
  • One Crescent construction site, inspection photo 3, 25 August 2025
  • One Crescent construction site, inspection photo 4, 25 August 2025

7 May 2025

24%+14 pts

  • One Crescent construction site, inspection photo 1, 7 May 2025
  • One Crescent construction site, inspection photo 2, 7 May 2025
  • One Crescent construction site, inspection photo 3, 7 May 2025
  • One Crescent construction site, inspection photo 4, 7 May 2025

10 October 2024

10%+9.1 pts

  • One Crescent construction site, inspection photo 1, 10 October 2024
  • One Crescent construction site, inspection photo 2, 10 October 2024
  • One Crescent construction site, inspection photo 3, 10 October 2024

10 October 2023

1.0%+1.0 pts

  • One Crescent construction site, inspection photo 1, 10 October 2023
  • One Crescent construction site, inspection photo 2, 10 October 2023
  • One Crescent construction site, inspection photo 3, 10 October 2023
  • One Crescent construction site, inspection photo 4, 10 October 2023

30 January 2023

0%

  • One Crescent construction site, inspection photo 1, 30 January 2023
  • One Crescent construction site, inspection photo 2, 30 January 2023

All 72 site photos, by inspection date

Context

Palm Jumeirah has 16 projects under construction, 45% built on average.

Own a unit in One Crescent?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the One Crescent handover date?
The registered completion date was March 2026, and the register still lists One Crescent as under construction. At the pace of its recent inspections the site would reach 100% around January 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on One Crescent?
One Crescent was 90% built at the site inspection on 28 October 2026. The site has been inspected 10 times since January 2023. The Land Department took 72 site photos at its inspections.
Is One Crescent delayed?
Yes. Its registered completion date of March 2026 has passed and the project is still listed as under construction.
Who is building One Crescent?
The registered developer is A H S Palm Development.
Which bank holds the escrow account for One Crescent?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.