Palm Beach Towers - 2 construction photos

107 photos taken by Dubai Land Department engineers at 14 site inspections, newest first. The percentage is how much of Palm Beach Towers - 2 was built on the day of each visit.

12 August 202682% built

21 May 202680% built

11 February 202677% built

23 October 202569% built

30 April 202564% built

23 January 202558% built

25 September 202448% built

28 May 202438% built

25 January 202436% built

22 November 202334% built

15 August 202333% built

12 April 202333% built

15 November 202233% built

20 June 202233% built

Back to Palm Beach Towers - 2 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.