Skip to content

Club Vista Mare construction progress

The register lists Club Vista Mare in Palm Jumeirah as complete, with a registered completion date of December 2015. Its last site inspection on record was in August 2016. The developer is The Palm - Jumeirah Co.

100%

Built, at the site inspection of 8 August 2016

Construction complete

Registered completion date
December 2015
Construction started
December 2013
First registered
June 2013
Community
Palm Jumeirah
Units
43
Escrow bank
Mashreq Bank
Name in Arabic
نادي فيستا ماري
Project number
1351
Site inspections
4

Schedule

The register lists Club Vista Mare as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201420152016
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

8 August 2016

100%+2.4 pts

  • Club Vista Mare construction site, inspection photo 1, 8 August 2016
  • Club Vista Mare construction site, inspection photo 2, 8 August 2016
  • Club Vista Mare construction site, inspection photo 3, 8 August 2016
  • Club Vista Mare construction site, inspection photo 4, 8 August 2016

10 April 2016

98%+17 pts

  • Club Vista Mare construction site, inspection photo 1, 10 April 2016
  • Club Vista Mare construction site, inspection photo 2, 10 April 2016
  • Club Vista Mare construction site, inspection photo 3, 10 April 2016
  • Club Vista Mare construction site, inspection photo 4, 10 April 2016

30 September 2015

81%+49 pts

  • Club Vista Mare construction site, inspection photo 1, 30 September 2015
  • Club Vista Mare construction site, inspection photo 2, 30 September 2015
  • Club Vista Mare construction site, inspection photo 3, 30 September 2015
  • Club Vista Mare construction site, inspection photo 4, 30 September 2015

17 December 2014

32%

  • Club Vista Mare construction site, inspection photo 1, 17 December 2014
  • Club Vista Mare construction site, inspection photo 2, 17 December 2014
  • Club Vista Mare construction site, inspection photo 3, 17 December 2014
  • Club Vista Mare construction site, inspection photo 4, 17 December 2014

All 30 site photos, by inspection date

Context

Palm Jumeirah has 16 projects under construction, 45% built on average.

The Palm - Jumeirah Co has 4 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Club Vista Mare?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Club Vista Mare handover date?
Construction of Club Vista Mare is recorded as complete, with a registered completion date of December 2015. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Club Vista Mare?
Club Vista Mare was 100% built at the site inspection on 8 August 2016. The site has been inspected 4 times since December 2014. The Land Department took 30 site photos at its inspections.
Is Club Vista Mare delayed?
The register lists construction as complete.
Who is building Club Vista Mare?
The registered developer is The Palm - Jumeirah Co. It has 4 other projects under construction in Dubai.
Which bank holds the escrow account for Club Vista Mare?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.