Ocean Bay By Samana Developers construction progress
The registered completion date for Ocean Bay By Samana Developers in Palm Deira is June 2028. At the last site inspection, in September 2026, it was 3.2% built. The developer is Samana Platinum Real Estate Development.
3.2%
Built, at the site inspection of 22 September 2026
Running behind its date
- Registered completion date
- June 2028
- Finish at recent pace
- October 2045
- Construction started
- September 2025
- First registered
- October 2025
- Community
- Palm Deira
- Units
- 143
- Escrow bank
- Emirates NBD
- Name in Arabic
- اوشن باي باي سامانا ديفيلوبرز
- Project number
- 3881
- Site inspections
- 4
Schedule
Between February 2026 and September 2026 the site added about 0.4 points a month. At that rate it would finish around October 2045, more than three months after its registered date of June 2028.
Site inspections
22 September 2026
3.2%+1.7 pts
22 June 2026
1.5%+1.5 pts
9 February 2026
0%+0.0 pts
11 September 2025
0%
Context
Palm Deira has 94 projects under construction, 24% built on average.
Samana Platinum Real Estate Development has 7 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Ocean Bay By Samana Developers?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Ocean Bay By Samana Developers handover date?
- The registered completion date is June 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2045. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Ocean Bay By Samana Developers?
- Ocean Bay By Samana Developers was 3.2% built at the site inspection on 22 September 2026. The site has been inspected 4 times since September 2025. The Land Department took 16 site photos at its inspections.
- Is Ocean Bay By Samana Developers delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
- Who is building Ocean Bay By Samana Developers?
- The registered developer is Samana Platinum Real Estate Development. It has 6 other projects under construction in Dubai.
- Which bank holds the escrow account for Ocean Bay By Samana Developers?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Ocean Crest By SdAlso by Samana Platinum Real Estate Development. 1.4%, Due June 2028.
- Greenfield By Samana DevelopersAlso by Samana Platinum Real Estate Development. 3.2%, Due October 2028.
- Greenfield 2 By Samana DevelopersAlso by Samana Platinum Real Estate Development. 0%, Due August 2029.
- Portside 2 By Samana DevelopersAlso by Samana Platinum Real Estate Development. 0%, Due December 2029.
- Bay Residences Dubai IslandsNearby in Palm Deira. 48%, Due October 2026, passed.
- Beach Residences Dubai IslandsNearby in Palm Deira. 29%.
- Bay Villas - Dubai IslandsNearby in Palm Deira. 23%, Due May 2027.
- Edgewater ResidencesNearby in Palm Deira. 48%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.





.jpeg&w=3840&q=75)