Greenfield By Samana Developers construction progress
The registered completion date for Greenfield By Samana Developers is October 2028. At the last site inspection, in October 2026, it was 3.2% built. The developer is Samana Platinum Real Estate Development.
3.2%
Built, at the site inspection of 28 October 2026
Running behind its date
- Registered completion date
- October 2028
- Finish at recent pace
- August 2048
- Construction started
- November 2025
- First registered
- December 2025
- Units
- 310
- Escrow bank
- Emirates NBD
- Name in Arabic
- جرينفيلد باي سامانا ديفيلوبرز
- Project number
- 4159
- Site inspections
- 3
Schedule
Between June 2026 and October 2026 the site added about 0.4 points a month. At that rate it would finish around August 2048, more than three months after its registered date of October 2028.
Site inspections
28 October 2026
3.2%+1.7 pts
11 June 2026
1.5%+1.5 pts
20 October 2025
0%
Context
Samana Platinum Real Estate Development has 7 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Greenfield By Samana Developers?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Greenfield By Samana Developers handover date?
- The registered completion date is October 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2048. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Greenfield By Samana Developers?
- Greenfield By Samana Developers was 3.2% built at the site inspection on 28 October 2026. The site has been inspected 3 times since October 2025. The Land Department took 8 site photos at its inspections.
- Is Greenfield By Samana Developers delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2028.
- Who is building Greenfield By Samana Developers?
- The registered developer is Samana Platinum Real Estate Development. It has 6 other projects under construction in Dubai.
- Which bank holds the escrow account for Greenfield By Samana Developers?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Ocean Crest By SdAlso by Samana Platinum Real Estate Development. 1.4%, Due June 2028.
- Ocean Bay By Samana DevelopersAlso by Samana Platinum Real Estate Development. 3.2%, Due June 2028.
- Greenfield 2 By Samana DevelopersAlso by Samana Platinum Real Estate Development. 0%, Due August 2029.
- Portside 2 By Samana DevelopersAlso by Samana Platinum Real Estate Development. 0%, Due December 2029.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.

.jpeg&w=3840&q=75)