Cotier House 2 By Imtiaz construction progress
The registered completion date for Cotier House 2 By Imtiaz in Palm Deira is April 2027. At the last site inspection, in October 2026, it was 20% built. The developer is Imtiaz Ug Real Estate Development.
20%
Built, at the site inspection of 23 October 2026
Running behind its date
- Registered completion date
- April 2027
- Finish at recent pace
- January 2031
- Construction started
- April 2025
- First registered
- April 2025
- Developer
- Imtiaz Ug Real Estate Development
- Community
- Palm Deira
- Units
- 128
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- كوتير هاوس 2 من امتياز
- Project number
- 3671
- Site inspections
- 6
Schedule
Between January 2026 and October 2026 the site added about 1.6 points a month. At that rate it would finish around January 2031, more than three months after its registered date of April 2027.
Site inspections
23 October 2026
20%+4.1 pts
20 July 2026
16%+7.2 pts
21 April 2026
8.9%+3.1 pts
19 January 2026
5.8%+4.0 pts
22 October 2025
1.8%+1.8 pts
9 April 2025
0%
Context
Palm Deira has 94 projects under construction, 24% built on average.
Imtiaz Ug Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Cotier House 2 By Imtiaz?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Cotier House 2 By Imtiaz handover date?
- The registered completion date is April 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Cotier House 2 By Imtiaz?
- Cotier House 2 By Imtiaz was 20% built at the site inspection on 23 October 2026. The site has been inspected 6 times since April 2025. The Land Department took 26 site photos at its inspections.
- Is Cotier House 2 By Imtiaz delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2027.
- Who is building Cotier House 2 By Imtiaz?
- The registered developer is Imtiaz Ug Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Cotier House 2 By Imtiaz?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Sunset Bay Five By ImtiazAlso by Imtiaz Ug Real Estate Development. 45%, Due October 2027.
- Bay Residences Dubai IslandsNearby in Palm Deira. 48%, Due October 2026, passed.
- Beach Residences Dubai IslandsNearby in Palm Deira. 29%.
- Bay Villas - Dubai IslandsNearby in Palm Deira. 23%, Due May 2027.
- Edgewater ResidencesNearby in Palm Deira. 48%.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)





.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)