Cotier House 2 By Imtiaz construction progress

The registered completion date for Cotier House 2 By Imtiaz in Palm Deira is April 2027. At the last site inspection, in October 2026, it was 20% built. The developer is Imtiaz Ug Real Estate Development.

20%

Built, at the site inspection of 23 October 2026

Running behind its date

Registered completion date
April 2027
Finish at recent pace
January 2031
Construction started
April 2025
First registered
April 2025
Developer
Imtiaz Ug Real Estate Development
Community
Palm Deira
Units
128
Escrow bank
First Abu Dhabi Bank
Name in Arabic
كوتير هاوس 2 من امتياز
Project number
3671
Site inspections
6

Schedule

Between January 2026 and October 2026 the site added about 1.6 points a month. At that rate it would finish around January 2031, more than three months after its registered date of April 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

23 October 2026

20%+4.1 pts

  • Cotier House 2 By Imtiaz construction site, inspection photo 1, 23 October 2026
  • Cotier House 2 By Imtiaz construction site, inspection photo 2, 23 October 2026
  • Cotier House 2 By Imtiaz construction site, inspection photo 3, 23 October 2026
  • Cotier House 2 By Imtiaz construction site, inspection photo 4, 23 October 2026

20 July 2026

16%+7.2 pts

  • Cotier House 2 By Imtiaz construction site, inspection photo 1, 20 July 2026
  • Cotier House 2 By Imtiaz construction site, inspection photo 2, 20 July 2026
  • Cotier House 2 By Imtiaz construction site, inspection photo 3, 20 July 2026
  • Cotier House 2 By Imtiaz construction site, inspection photo 4, 20 July 2026

21 April 2026

8.9%+3.1 pts

  • Cotier House 2 By Imtiaz construction site, inspection photo 1, 21 April 2026
  • Cotier House 2 By Imtiaz construction site, inspection photo 2, 21 April 2026
  • Cotier House 2 By Imtiaz construction site, inspection photo 3, 21 April 2026
  • Cotier House 2 By Imtiaz construction site, inspection photo 4, 21 April 2026

19 January 2026

5.8%+4.0 pts

  • Cotier House 2 By Imtiaz construction site, inspection photo 1, 19 January 2026
  • Cotier House 2 By Imtiaz construction site, inspection photo 2, 19 January 2026
  • Cotier House 2 By Imtiaz construction site, inspection photo 3, 19 January 2026
  • Cotier House 2 By Imtiaz construction site, inspection photo 4, 19 January 2026

22 October 2025

1.8%+1.8 pts

  • Cotier House 2 By Imtiaz construction site, inspection photo 1, 22 October 2025
  • Cotier House 2 By Imtiaz construction site, inspection photo 2, 22 October 2025
  • Cotier House 2 By Imtiaz construction site, inspection photo 3, 22 October 2025
  • Cotier House 2 By Imtiaz construction site, inspection photo 4, 22 October 2025

9 April 2025

0%

  • Cotier House 2 By Imtiaz construction site, inspection photo 1, 9 April 2025

All 26 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Imtiaz Ug Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Cotier House 2 By Imtiaz?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Cotier House 2 By Imtiaz handover date?
The registered completion date is April 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Cotier House 2 By Imtiaz?
Cotier House 2 By Imtiaz was 20% built at the site inspection on 23 October 2026. The site has been inspected 6 times since April 2025. The Land Department took 26 site photos at its inspections.
Is Cotier House 2 By Imtiaz delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of April 2027.
Who is building Cotier House 2 By Imtiaz?
The registered developer is Imtiaz Ug Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Cotier House 2 By Imtiaz?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.