22 photos taken by Dubai Land Department engineers at 5 site inspections, newest first. The percentage is how much of Cotier House 2 By Imtiaz was built on the day of each visit.

20 July 202616% built

21 April 20268.9% built

19 January 20265.8% built

22 October 20251.8% built

9 April 20250% built

Back to Cotier House 2 By Imtiaz construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.