Sunset Bay Five By Imtiaz construction progress

The registered completion date for Sunset Bay Five By Imtiaz in Palm Deira is October 2027. At the last site inspection, in October 2026, it was 45% built. The developer is Imtiaz Ug Real Estate Development.

45%

Built, at the site inspection of 5 October 2026

On pace for its date

Registered completion date
October 2027
Finish at recent pace
January 2028
Construction started
June 2025
First registered
July 2025
Developer
Imtiaz Ug Real Estate Development
Community
Palm Deira
Units
62
Escrow bank
First Abu Dhabi Bank
Name in Arabic
صن سيت باي فايف من امتياز
Project number
3811
Site inspections
6

Schedule

Since October 2025 Sunset Bay Five By Imtiaz has added about 3.7 points a month. That puts 100% around January 2028, within three months of its registered completion date of October 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

5 October 2026

45%+12 pts

  • Sunset Bay Five By Imtiaz construction site, inspection photo 1, 5 October 2026
  • Sunset Bay Five By Imtiaz construction site, inspection photo 2, 5 October 2026
  • Sunset Bay Five By Imtiaz construction site, inspection photo 3, 5 October 2026
  • Sunset Bay Five By Imtiaz construction site, inspection photo 4, 5 October 2026

9 July 2026

33%+16 pts

  • Sunset Bay Five By Imtiaz construction site, inspection photo 1, 9 July 2026
  • Sunset Bay Five By Imtiaz construction site, inspection photo 2, 9 July 2026
  • Sunset Bay Five By Imtiaz construction site, inspection photo 3, 9 July 2026
  • Sunset Bay Five By Imtiaz construction site, inspection photo 4, 9 July 2026

14 April 2026

16%+9.6 pts

  • Sunset Bay Five By Imtiaz construction site, inspection photo 1, 14 April 2026
  • Sunset Bay Five By Imtiaz construction site, inspection photo 2, 14 April 2026
  • Sunset Bay Five By Imtiaz construction site, inspection photo 3, 14 April 2026
  • Sunset Bay Five By Imtiaz construction site, inspection photo 4, 14 April 2026

9 January 2026

6.7%+5.6 pts

  • Sunset Bay Five By Imtiaz construction site, inspection photo 1, 9 January 2026
  • Sunset Bay Five By Imtiaz construction site, inspection photo 2, 9 January 2026
  • Sunset Bay Five By Imtiaz construction site, inspection photo 3, 9 January 2026
  • Sunset Bay Five By Imtiaz construction site, inspection photo 4, 9 January 2026

10 October 2025

1.0%+1.0 pts

  • Sunset Bay Five By Imtiaz construction site, inspection photo 1, 10 October 2025
  • Sunset Bay Five By Imtiaz construction site, inspection photo 2, 10 October 2025

4 June 2025

0%

  • Sunset Bay Five By Imtiaz construction site, inspection photo 1, 4 June 2025
  • Sunset Bay Five By Imtiaz construction site, inspection photo 2, 4 June 2025

All 30 site photos, by inspection date

Context

Palm Deira has 94 projects under construction, 24% built on average.

Imtiaz Ug Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Sunset Bay Five By Imtiaz?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Sunset Bay Five By Imtiaz handover date?
The registered completion date is October 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Sunset Bay Five By Imtiaz?
Sunset Bay Five By Imtiaz was 45% built at the site inspection on 5 October 2026. The site has been inspected 6 times since June 2025. The Land Department took 30 site photos at its inspections.
Is Sunset Bay Five By Imtiaz delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of October 2027.
Who is building Sunset Bay Five By Imtiaz?
The registered developer is Imtiaz Ug Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Sunset Bay Five By Imtiaz?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.