The Woodland Residences construction photos
42 photos from 7 site inspections, newest first. The percentage is how much of The Woodland Residences was built on the day of each visit.
2 September 202675% built
22 April 202656% built
15 January 202644% built
1 October 202526% built
28 May 20258.7% built
5 December 20243.5% built
24 November 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.