Api- Barsha Residential Tower construction progress
Api- Barsha Residential Tower in Al Barsha First was registered to complete in October 2025 and is still under construction. At the last site inspection, in February 2026, it was 93% built. The developer is Dubai General Properties.
93%
Built, at the site inspection of 17 February 2026
13 months past its registered completion date
- Registered completion date
- October 2025
- Finish at recent pace
- September 2026
- Construction started
- August 2021
- First registered
- January 2025
- Developer
- Dubai General Properties
- Community
- Al Barsha First
- Units
- 335
- Escrow bank
- Emirates NBD
- Name in Arabic
- إيه بي آي- برشاء ريزيدنشال تاور
- Project number
- 3417
- Site inspections
- 3
Schedule
Api- Barsha Residential Tower was registered to complete in October 2025, 13 months ago, and is still under construction. Over the last year of inspections it has added about 1.0 points a month. Kept at that rate, the site would reach 100% around September 2026.
Site inspections
17 February 2026
93%+4.9 pts
23 September 2025
88%+9.1 pts
27 December 2024
79%
Context
Al Barsha First has 2 projects under construction, 59% built on average.
Dubai General Properties has 2 projects under construction in Dubai; 2 have passed their registered completion date.
Own a unit in Api- Barsha Residential Tower?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Api- Barsha Residential Tower handover date?
- The registered completion date was October 2025, and the register still lists Api- Barsha Residential Tower as under construction. At the pace of its recent inspections the site would reach 100% around September 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Api- Barsha Residential Tower?
- Api- Barsha Residential Tower was 93% built at the site inspection on 17 February 2026. The site has been inspected 3 times since December 2024. The Land Department took 25 site photos at its inspections.
- Is Api- Barsha Residential Tower delayed?
- Yes. Its registered completion date of October 2025 has passed and the project is still listed as under construction.
- Who is building Api- Barsha Residential Tower?
- The registered developer is Dubai General Properties. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Api- Barsha Residential Tower?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Mews MansionsAlso by Dubai General Properties. 56%, Due December 2025, passed.
- Mas Barsha ResidencyNearby in Al Barsha First. 26%, Due November 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.



.jpeg&w=3840&q=75)