Api- Barsha Residential Tower construction progress

Api- Barsha Residential Tower in Al Barsha First is 93% built at the Land Department inspection of February 2026. Developer Dubai General Properties. Completion registered for October 2025.

93%

Built, at the Land Department site inspection of 17 February 2026

11 months past its registered completion date

Completion date (Land Department)
October 2025
Finish at recent pace
September 2026
Construction started
August 2021
Registered with the Land Department
January 2025
Developer
Dubai General Properties
Community
Al Barsha First
Units
335
Escrow bank
Emirates NBD
Name in Arabic
إيه بي آي- برشاء ريزيدنشال تاور
Land Department project number
3417
Land Department site inspections
3

Schedule

Api- Barsha Residential Tower was registered to complete in October 2025, 11 months ago, and is still under construction. Over the last year of inspections it has added about 1.0 points a month. Kept at that rate, the site would reach 100% around September 2026.

0%25%50%75%100%20222023202420252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

17 February 2026

93%+4.9 pts

  • Api- Barsha Residential Tower construction site, Land Department inspection photo 1, 17 February 2026
  • Api- Barsha Residential Tower construction site, Land Department inspection photo 2, 17 February 2026
  • Api- Barsha Residential Tower construction site, Land Department inspection photo 3, 17 February 2026
  • Api- Barsha Residential Tower construction site, Land Department inspection photo 4, 17 February 2026

23 September 2025

88%+9.1 pts

  • Api- Barsha Residential Tower construction site, Land Department inspection photo 1, 23 September 2025
  • Api- Barsha Residential Tower construction site, Land Department inspection photo 2, 23 September 2025
  • Api- Barsha Residential Tower construction site, Land Department inspection photo 3, 23 September 2025
  • Api- Barsha Residential Tower construction site, Land Department inspection photo 4, 23 September 2025

27 December 2024

79%

  • Api- Barsha Residential Tower construction site, Land Department inspection photo 1, 27 December 2024
  • Api- Barsha Residential Tower construction site, Land Department inspection photo 2, 27 December 2024
  • Api- Barsha Residential Tower construction site, Land Department inspection photo 3, 27 December 2024
  • Api- Barsha Residential Tower construction site, Land Department inspection photo 4, 27 December 2024

All 25 site photos, by inspection date

Context

Al Barsha First has 2 projects under construction, 59% built on average. Api- Barsha Residential Tower is ahead of that average.

Dubai General Properties has 2 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Api- Barsha Residential Tower?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Api- Barsha Residential Tower be completed?
The completion date registered with the Dubai Land Department is October 2025. At the pace of its recent inspections the site would reach 100% around September 2026. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Api- Barsha Residential Tower is built?
93%, measured at the Land Department site inspection on 17 February 2026. The Land Department engineers have inspected the site 3 times since December 2024.
Is Api- Barsha Residential Tower delayed?
Yes. Its registered completion date of October 2025 has passed and the Land Department still lists it as under construction.
Who is building Api- Barsha Residential Tower?
The registered developer is Dubai General Properties. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Api- Barsha Residential Tower?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.