Skip to content

Azizi Riviera Reve construction photos

66 photos taken by Dubai Land Department engineers at 10 site inspections, newest first. The percentage is how much of Azizi Riviera Reve was built on the day of each visit.

1 July 202677% built

4 December 202563% built

11 August 202553% built

18 April 202540% built

19 November 202431% built

3 October 202428% built

26 June 202415% built

31 August 20232.2% built

6 April 20231.1% built

2 August 20221.0% built

Back to Azizi Riviera Reve construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.