Azizi Riviera Reve construction photos

66 photos from 10 site inspections, newest first. The percentage is how much of Azizi Riviera Reve was built on the day of each visit.

1 July 202677% built

4 December 202563% built

11 August 202553% built

18 April 202540% built

19 November 202431% built

3 October 202428% built

26 June 202415% built

31 August 20232.2% built

6 April 20231.1% built

2 August 20221.0% built