Azizi Riviera 23 construction progress

The register lists Azizi Riviera 23 in Meydan One Community as complete, with a registered completion date of December 2022. Its last site inspection on record was in October 2023. The developer is Azizi Developments.

100%

Built, at the site inspection of 17 October 2023

Construction complete

Registered completion date
December 2022
Construction started
November 2017
First registered
December 2017
Units
248
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
عزيزي ريفيرا 23
Project number
2009
Site inspections
8

Schedule

The register lists Azizi Riviera 23 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201820202022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

17 October 2023

100%+26 pts

  • Azizi Riviera 23 construction site, inspection photo 1, 17 October 2023
  • Azizi Riviera 23 construction site, inspection photo 2, 17 October 2023
  • Azizi Riviera 23 construction site, inspection photo 3, 17 October 2023
  • Azizi Riviera 23 construction site, inspection photo 4, 17 October 2023

19 April 2022

74%+5.8 pts

  • Azizi Riviera 23 construction site, inspection photo 1, 19 April 2022
  • Azizi Riviera 23 construction site, inspection photo 2, 19 April 2022
  • Azizi Riviera 23 construction site, inspection photo 3, 19 April 2022
  • Azizi Riviera 23 construction site, inspection photo 4, 19 April 2022

27 October 2021

68%+20 pts

  • Azizi Riviera 23 construction site, inspection photo 1, 27 October 2021
  • Azizi Riviera 23 construction site, inspection photo 2, 27 October 2021
  • Azizi Riviera 23 construction site, inspection photo 3, 27 October 2021
  • Azizi Riviera 23 construction site, inspection photo 4, 27 October 2021

27 April 2021

48%+7.0 pts

  • Azizi Riviera 23 construction site, inspection photo 1, 27 April 2021
  • Azizi Riviera 23 construction site, inspection photo 2, 27 April 2021
  • Azizi Riviera 23 construction site, inspection photo 3, 27 April 2021
  • Azizi Riviera 23 construction site, inspection photo 4, 27 April 2021

30 September 2020

41%+21 pts

  • Azizi Riviera 23 construction site, inspection photo 1, 30 September 2020
  • Azizi Riviera 23 construction site, inspection photo 2, 30 September 2020
  • Azizi Riviera 23 construction site, inspection photo 3, 30 September 2020
  • Azizi Riviera 23 construction site, inspection photo 4, 30 September 2020

19 December 2019

20%+9.5 pts

  • Azizi Riviera 23 construction site, inspection photo 1, 19 December 2019
  • Azizi Riviera 23 construction site, inspection photo 2, 19 December 2019
  • Azizi Riviera 23 construction site, inspection photo 3, 19 December 2019
  • Azizi Riviera 23 construction site, inspection photo 4, 19 December 2019

4 September 2019

10%+0.4 pts

  • Azizi Riviera 23 construction site, inspection photo 1, 4 September 2019
  • Azizi Riviera 23 construction site, inspection photo 2, 4 September 2019
  • Azizi Riviera 23 construction site, inspection photo 3, 4 September 2019
  • Azizi Riviera 23 construction site, inspection photo 4, 4 September 2019

20 November 2018

10%

  • Azizi Riviera 23 construction site, inspection photo 1, 20 November 2018
  • Azizi Riviera 23 construction site, inspection photo 2, 20 November 2018
  • Azizi Riviera 23 construction site, inspection photo 3, 20 November 2018
  • Azizi Riviera 23 construction site, inspection photo 4, 20 November 2018

All 72 site photos, by inspection date

Context

Meydan One Community has 9 projects under construction, 76% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Riviera 23?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Azizi Riviera 23 handover date?
Construction of Azizi Riviera 23 is recorded as complete, with a registered completion date of December 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Azizi Riviera 23?
Azizi Riviera 23 was 100% built at the site inspection on 17 October 2023. The site has been inspected 8 times since November 2018. The Land Department took 72 site photos at its inspections.
Is Azizi Riviera 23 delayed?
The register lists construction as complete.
Who is building Azizi Riviera 23?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Riviera 23?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.