Azizi Riviera 23 construction photos
72 photos from 8 site inspections, newest first. The percentage is how much of Azizi Riviera 23 was built on the day of each visit.
17 October 2023100% built
19 April 202274% built
27 October 202168% built
27 April 202148% built
30 September 202041% built
19 December 201920% built
4 September 201910% built
20 November 201810% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.