Skip to content

Azizi Riviera 13 construction progress

The register lists Azizi Riviera 13 in Meydan One Community as complete, with a registered completion date of April 2022. Its last site inspection on record was in November 2022. The developer is Azizi Developments.

100%

Built, at the site inspection of 10 November 2022

Construction complete

Registered completion date
April 2022
Construction started
October 2017
First registered
September 2017
Units
234
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
عزيزي ريفييرا 13
Project number
1976
Site inspections
9

Schedule

The register lists Azizi Riviera 13 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%20182019202020212022
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

10 November 2022

100%+14 pts

  • Azizi Riviera 13 construction site, inspection photo 1, 10 November 2022
  • Azizi Riviera 13 construction site, inspection photo 2, 10 November 2022
  • Azizi Riviera 13 construction site, inspection photo 3, 10 November 2022
  • Azizi Riviera 13 construction site, inspection photo 4, 10 November 2022

1 March 2022

86%+9.0 pts

  • Azizi Riviera 13 construction site, inspection photo 1, 1 March 2022
  • Azizi Riviera 13 construction site, inspection photo 2, 1 March 2022
  • Azizi Riviera 13 construction site, inspection photo 3, 1 March 2022
  • Azizi Riviera 13 construction site, inspection photo 4, 1 March 2022

1 September 2021

77%+6.4 pts

  • Azizi Riviera 13 construction site, inspection photo 1, 1 September 2021
  • Azizi Riviera 13 construction site, inspection photo 2, 1 September 2021
  • Azizi Riviera 13 construction site, inspection photo 3, 1 September 2021
  • Azizi Riviera 13 construction site, inspection photo 4, 1 September 2021

6 April 2021

71%+8.2 pts

  • Azizi Riviera 13 construction site, inspection photo 1, 6 April 2021
  • Azizi Riviera 13 construction site, inspection photo 2, 6 April 2021
  • Azizi Riviera 13 construction site, inspection photo 3, 6 April 2021
  • Azizi Riviera 13 construction site, inspection photo 4, 6 April 2021

11 November 2020

63%+7.0 pts

  • Azizi Riviera 13 construction site, inspection photo 1, 11 November 2020
  • Azizi Riviera 13 construction site, inspection photo 2, 11 November 2020
  • Azizi Riviera 13 construction site, inspection photo 3, 11 November 2020
  • Azizi Riviera 13 construction site, inspection photo 4, 11 November 2020

14 July 2020

55%+5.4 pts

  • Azizi Riviera 13 construction site, inspection photo 1, 14 July 2020
  • Azizi Riviera 13 construction site, inspection photo 2, 14 July 2020
  • Azizi Riviera 13 construction site, inspection photo 3, 14 July 2020
  • Azizi Riviera 13 construction site, inspection photo 4, 14 July 2020

2 February 2020

50%+20 pts

  • Azizi Riviera 13 construction site, inspection photo 1, 2 February 2020
  • Azizi Riviera 13 construction site, inspection photo 2, 2 February 2020
  • Azizi Riviera 13 construction site, inspection photo 3, 2 February 2020
  • Azizi Riviera 13 construction site, inspection photo 4, 2 February 2020

25 April 2019

30%+10 pts

  • Azizi Riviera 13 construction site, inspection photo 1, 25 April 2019
  • Azizi Riviera 13 construction site, inspection photo 2, 25 April 2019
  • Azizi Riviera 13 construction site, inspection photo 3, 25 April 2019
  • Azizi Riviera 13 construction site, inspection photo 4, 25 April 2019

25 October 2018

20%

  • Azizi Riviera 13 construction site, inspection photo 1, 25 October 2018
  • Azizi Riviera 13 construction site, inspection photo 2, 25 October 2018
  • Azizi Riviera 13 construction site, inspection photo 3, 25 October 2018
  • Azizi Riviera 13 construction site, inspection photo 4, 25 October 2018

All 95 site photos, by inspection date

Context

Meydan One Community has 9 projects under construction, 76% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Riviera 13?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Azizi Riviera 13 handover date?
Construction of Azizi Riviera 13 is recorded as complete, with a registered completion date of April 2022. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Azizi Riviera 13?
Azizi Riviera 13 was 100% built at the site inspection on 10 November 2022. The site has been inspected 9 times since October 2018. The Land Department took 95 site photos at its inspections.
Is Azizi Riviera 13 delayed?
The register lists construction as complete.
Who is building Azizi Riviera 13?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Riviera 13?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.