Azizi Riviera 13 construction photos

95 photos from 9 site inspections, newest first. The percentage is how much of Azizi Riviera 13 was built on the day of each visit.

10 November 2022100% built

1 March 202286% built

1 September 202177% built

6 April 202171% built

11 November 202063% built

14 July 202055% built

2 February 202050% built

25 April 201930% built

25 October 201820% built

Back to Azizi Riviera 13 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.