Azizi Riviera 1 construction progress

The register lists Azizi Riviera 1 in Meydan One Community as complete, with a registered completion date of July 2024. Its last site inspection on record was in July 2024. The developer is Azizi Developments.

100%

Built, at the site inspection of 25 July 2024

Construction complete

Registered completion date
July 2024
Construction started
October 2017
First registered
September 2017
Units
378
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
عزيزي ريفييرا 1
Project number
1958
Site inspections
13

Schedule

The register lists Azizi Riviera 1 as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%2018202020222024
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

25 July 2024

100%+19 pts

  • Azizi Riviera 1 construction site, inspection photo 1, 25 July 2024
  • Azizi Riviera 1 construction site, inspection photo 2, 25 July 2024
  • Azizi Riviera 1 construction site, inspection photo 3, 25 July 2024
  • Azizi Riviera 1 construction site, inspection photo 4, 25 July 2024

15 May 2023

81%+6.1 pts

  • Azizi Riviera 1 construction site, inspection photo 1, 15 May 2023
  • Azizi Riviera 1 construction site, inspection photo 2, 15 May 2023
  • Azizi Riviera 1 construction site, inspection photo 3, 15 May 2023
  • Azizi Riviera 1 construction site, inspection photo 4, 15 May 2023

22 August 2022

74%+6.1 pts

  • Azizi Riviera 1 construction site, inspection photo 1, 22 August 2022
  • Azizi Riviera 1 construction site, inspection photo 2, 22 August 2022
  • Azizi Riviera 1 construction site, inspection photo 3, 22 August 2022
  • Azizi Riviera 1 construction site, inspection photo 4, 22 August 2022

21 February 2022

68%+2.3 pts

  • Azizi Riviera 1 construction site, inspection photo 1, 21 February 2022
  • Azizi Riviera 1 construction site, inspection photo 2, 21 February 2022
  • Azizi Riviera 1 construction site, inspection photo 3, 21 February 2022
  • Azizi Riviera 1 construction site, inspection photo 4, 21 February 2022

6 October 2021

66%+10 pts

  • Azizi Riviera 1 construction site, inspection photo 1, 6 October 2021
  • Azizi Riviera 1 construction site, inspection photo 2, 6 October 2021
  • Azizi Riviera 1 construction site, inspection photo 3, 6 October 2021
  • Azizi Riviera 1 construction site, inspection photo 4, 6 October 2021

17 June 2021

56%+16 pts

  • Azizi Riviera 1 construction site, inspection photo 1, 17 June 2021
  • Azizi Riviera 1 construction site, inspection photo 2, 17 June 2021
  • Azizi Riviera 1 construction site, inspection photo 3, 17 June 2021
  • Azizi Riviera 1 construction site, inspection photo 4, 17 June 2021

26 January 2021

40%+22 pts

  • Azizi Riviera 1 construction site, inspection photo 1, 26 January 2021
  • Azizi Riviera 1 construction site, inspection photo 2, 26 January 2021
  • Azizi Riviera 1 construction site, inspection photo 3, 26 January 2021
  • Azizi Riviera 1 construction site, inspection photo 4, 26 January 2021

17 June 2020

18%+5.0 pts

  • Azizi Riviera 1 construction site, inspection photo 1, 17 June 2020
  • Azizi Riviera 1 construction site, inspection photo 2, 17 June 2020
  • Azizi Riviera 1 construction site, inspection photo 3, 17 June 2020
  • Azizi Riviera 1 construction site, inspection photo 4, 17 June 2020

24 March 2020

13%+4.2 pts

  • Azizi Riviera 1 construction site, inspection photo 1, 24 March 2020
  • Azizi Riviera 1 construction site, inspection photo 2, 24 March 2020
  • Azizi Riviera 1 construction site, inspection photo 3, 24 March 2020
  • Azizi Riviera 1 construction site, inspection photo 4, 24 March 2020

9 December 2019

8.6%+0.7 pts

  • Azizi Riviera 1 construction site, inspection photo 1, 9 December 2019
  • Azizi Riviera 1 construction site, inspection photo 2, 9 December 2019
  • Azizi Riviera 1 construction site, inspection photo 3, 9 December 2019
  • Azizi Riviera 1 construction site, inspection photo 4, 9 December 2019

All 101 site photos, by inspection date

Context

Meydan One Community has 9 projects under construction, 76% built on average.

Azizi Developments has 56 projects under construction in Dubai; 10 have passed their registered completion date.

Own a unit in Azizi Riviera 1?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Azizi Riviera 1 handover date?
Construction of Azizi Riviera 1 is recorded as complete, with a registered completion date of July 2024. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Azizi Riviera 1?
Azizi Riviera 1 was 100% built at the site inspection on 25 July 2024. The site has been inspected 13 times since April 2018. The Land Department took 101 site photos at its inspections.
Is Azizi Riviera 1 delayed?
The register lists construction as complete.
Who is building Azizi Riviera 1?
The registered developer is Azizi Developments. It has 56 other projects under construction in Dubai.
Which bank holds the escrow account for Azizi Riviera 1?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.