Azizi Riviera 1 construction photos

101 photos from 13 site inspections, newest first. The percentage is how much of Azizi Riviera 1 was built on the day of each visit.

25 July 2024100% built

15 May 202381% built

22 August 202274% built

21 February 202268% built

6 October 202166% built

17 June 202156% built

26 January 202140% built

17 June 202018% built

24 March 202013% built

9 December 20198.6% built

9 July 20197.9% built

3 January 20197.9% built

3 April 20183.1% built

Back to Azizi Riviera 1 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.