Wadi 645 construction photos

43 photos taken by Dubai Land Department engineers at 7 site inspections, newest first. The percentage is how much of Wadi 645 was built on the day of each visit.

18 August 202655% built

21 May 202642% built

9 February 202629% built

4 November 202519% built

25 May 202511% built

11 February 20253.4% built

15 March 20240% built

Back to Wadi 645 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.