Tulip Oasis 11 construction progress
Tulip Oasis 11 in Majan was registered to complete in June 2026 and is still under construction. At the last site inspection, in October 2026, it was 93% built. The developer is A M E Real Estate Development.
93%
Built, at the site inspection of 13 October 2026
5 months past its registered completion date
- Registered completion date
- June 2026
- Finish at recent pace
- November 2026
- Construction started
- February 2024
- First registered
- March 2025
- Developer
- A M E Real Estate Development
- Community
- Majan
- Units
- 108
- Escrow bank
- Emirates Islamic Bank
- Name in Arabic
- توليب أويسس 11
- Project number
- 3538
- Site inspections
- 6
Schedule
Tulip Oasis 11 was registered to complete in June 2026, 5 months ago, and is still under construction. Over the last year of inspections it has added about 4.4 points a month. Kept at that rate, the site would reach 100% around November 2026.
Site inspections
13 October 2026
93%+23 pts
6 July 2026
70%+7.6 pts
2 April 2026
63%+12 pts
22 December 2025
50%+4.4 pts
15 September 2025
46%+16 pts
6 February 2025
30%
Context
Majan has 25 projects under construction, 28% built on average.
Own a unit in Tulip Oasis 11?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Tulip Oasis 11 handover date?
- The registered completion date was June 2026, and the register still lists Tulip Oasis 11 as under construction. At the pace of its recent inspections the site would reach 100% around November 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Tulip Oasis 11?
- Tulip Oasis 11 was 93% built at the site inspection on 13 October 2026. The site has been inspected 6 times since February 2025. The Land Department took 51 site photos at its inspections.
- Is Tulip Oasis 11 delayed?
- Yes. Its registered completion date of June 2026 has passed and the project is still listed as under construction.
- Who is building Tulip Oasis 11?
- The registered developer is A M E Real Estate Development.
- Which bank holds the escrow account for Tulip Oasis 11?
- Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Sherena Residence 2Nearby in Majan. 82%, Due August 2022, passed.
- Samana Barari ViewsNearby in Majan. 32%, Due March 2027.
- Samana Barari Views 2Nearby in Majan. 26%.
- Barari Parkview By Al MawaredNearby in Majan. 45%, Due December 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.