Tulip Oasis 11 construction progress

Tulip Oasis 11 in Majan was registered to complete in June 2026 and is still under construction. At the last site inspection, in October 2026, it was 93% built. The developer is A M E Real Estate Development.

93%

Built, at the site inspection of 13 October 2026

5 months past its registered completion date

Registered completion date
June 2026
Finish at recent pace
November 2026
Construction started
February 2024
First registered
March 2025
Developer
A M E Real Estate Development
Community
Majan
Units
108
Escrow bank
Emirates Islamic Bank
Name in Arabic
توليب أويسس 11
Project number
3538
Site inspections
6

Schedule

Tulip Oasis 11 was registered to complete in June 2026, 5 months ago, and is still under construction. Over the last year of inspections it has added about 4.4 points a month. Kept at that rate, the site would reach 100% around November 2026.

0%25%50%75%100%20252026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

13 October 2026

93%+23 pts

  • Tulip Oasis 11 construction site, inspection photo 1, 13 October 2026
  • Tulip Oasis 11 construction site, inspection photo 2, 13 October 2026
  • Tulip Oasis 11 construction site, inspection photo 3, 13 October 2026
  • Tulip Oasis 11 construction site, inspection photo 4, 13 October 2026

6 July 2026

70%+7.6 pts

  • Tulip Oasis 11 construction site, inspection photo 1, 6 July 2026
  • Tulip Oasis 11 construction site, inspection photo 2, 6 July 2026
  • Tulip Oasis 11 construction site, inspection photo 3, 6 July 2026
  • Tulip Oasis 11 construction site, inspection photo 4, 6 July 2026

2 April 2026

63%+12 pts

  • Tulip Oasis 11 construction site, inspection photo 1, 2 April 2026
  • Tulip Oasis 11 construction site, inspection photo 2, 2 April 2026
  • Tulip Oasis 11 construction site, inspection photo 3, 2 April 2026
  • Tulip Oasis 11 construction site, inspection photo 4, 2 April 2026

22 December 2025

50%+4.4 pts

  • Tulip Oasis 11 construction site, inspection photo 1, 22 December 2025
  • Tulip Oasis 11 construction site, inspection photo 2, 22 December 2025
  • Tulip Oasis 11 construction site, inspection photo 3, 22 December 2025
  • Tulip Oasis 11 construction site, inspection photo 4, 22 December 2025

15 September 2025

46%+16 pts

  • Tulip Oasis 11 construction site, inspection photo 1, 15 September 2025
  • Tulip Oasis 11 construction site, inspection photo 2, 15 September 2025
  • Tulip Oasis 11 construction site, inspection photo 3, 15 September 2025
  • Tulip Oasis 11 construction site, inspection photo 4, 15 September 2025

6 February 2025

30%

  • Tulip Oasis 11 construction site, inspection photo 1, 6 February 2025
  • Tulip Oasis 11 construction site, inspection photo 2, 6 February 2025
  • Tulip Oasis 11 construction site, inspection photo 3, 6 February 2025
  • Tulip Oasis 11 construction site, inspection photo 4, 6 February 2025

All 51 site photos, by inspection date

Context

Majan has 25 projects under construction, 28% built on average.

Own a unit in Tulip Oasis 11?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Tulip Oasis 11 handover date?
The registered completion date was June 2026, and the register still lists Tulip Oasis 11 as under construction. At the pace of its recent inspections the site would reach 100% around November 2026. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Tulip Oasis 11?
Tulip Oasis 11 was 93% built at the site inspection on 13 October 2026. The site has been inspected 6 times since February 2025. The Land Department took 51 site photos at its inspections.
Is Tulip Oasis 11 delayed?
Yes. Its registered completion date of June 2026 has passed and the project is still listed as under construction.
Who is building Tulip Oasis 11?
The registered developer is A M E Real Estate Development.
Which bank holds the escrow account for Tulip Oasis 11?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.