Tulip Oasis 11 construction progress

Tulip Oasis 11 in Majan is 70% built at the Land Department inspection of July 2026. Developer A M E Real Estate Development. Completion registered for June 2026.

70%

Built, at the Land Department site inspection of 6 July 2026

3 months past its registered completion date

Completion date (Land Department)
June 2026
Finish at recent pace
July 2027
Construction started
February 2024
Registered with the Land Department
March 2025
Developer
A M E Real Estate Development
Community
Majan
Units
108
Escrow bank
Emirates Islamic Bank
Name in Arabic
توليب أويسس 11
Land Department project number
3538
Land Department site inspections
5

Schedule

Tulip Oasis 11 was registered to complete in June 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 2.5 points a month. Kept at that rate, the site would reach 100% around July 2027.

0%25%50%75%100%20252026
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

6 July 2026

70%+7.6 pts

  • Tulip Oasis 11 construction site, Land Department inspection photo 1, 6 July 2026
  • Tulip Oasis 11 construction site, Land Department inspection photo 2, 6 July 2026
  • Tulip Oasis 11 construction site, Land Department inspection photo 3, 6 July 2026
  • Tulip Oasis 11 construction site, Land Department inspection photo 4, 6 July 2026

2 April 2026

63%+12 pts

  • Tulip Oasis 11 construction site, Land Department inspection photo 1, 2 April 2026
  • Tulip Oasis 11 construction site, Land Department inspection photo 2, 2 April 2026
  • Tulip Oasis 11 construction site, Land Department inspection photo 3, 2 April 2026
  • Tulip Oasis 11 construction site, Land Department inspection photo 4, 2 April 2026

22 December 2025

50%+4.4 pts

  • Tulip Oasis 11 construction site, Land Department inspection photo 1, 22 December 2025
  • Tulip Oasis 11 construction site, Land Department inspection photo 2, 22 December 2025
  • Tulip Oasis 11 construction site, Land Department inspection photo 3, 22 December 2025
  • Tulip Oasis 11 construction site, Land Department inspection photo 4, 22 December 2025

15 September 2025

46%+16 pts

  • Tulip Oasis 11 construction site, Land Department inspection photo 1, 15 September 2025
  • Tulip Oasis 11 construction site, Land Department inspection photo 2, 15 September 2025
  • Tulip Oasis 11 construction site, Land Department inspection photo 3, 15 September 2025
  • Tulip Oasis 11 construction site, Land Department inspection photo 4, 15 September 2025

6 February 2025

30%

  • Tulip Oasis 11 construction site, Land Department inspection photo 1, 6 February 2025
  • Tulip Oasis 11 construction site, Land Department inspection photo 2, 6 February 2025
  • Tulip Oasis 11 construction site, Land Department inspection photo 3, 6 February 2025
  • Tulip Oasis 11 construction site, Land Department inspection photo 4, 6 February 2025

All 41 site photos, by inspection date

Context

Majan has 25 projects under construction, 24% built on average.

Own a unit in Tulip Oasis 11?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Tulip Oasis 11 be completed?
The completion date registered with the Dubai Land Department is June 2026. At the pace of its recent inspections the site would reach 100% around July 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Tulip Oasis 11 is built?
70%, measured at the Land Department site inspection on 6 July 2026. The Land Department engineers have inspected the site 5 times since February 2025.
Is Tulip Oasis 11 delayed?
Yes. Its registered completion date of June 2026 has passed and the Land Department still lists it as under construction.
Who is building Tulip Oasis 11?
The registered developer is A M E Real Estate Development.
Which bank holds the escrow account for Tulip Oasis 11?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.