Rabdan Gates construction progress

The registered completion date for Rabdan Gates in Majan is June 2028. At the last site inspection, in October 2026, it was 5.2% built. The developer is Rabdan Real Estate Development.

5.2%

Built, at the site inspection of 27 October 2026

Running behind its date

Registered completion date
June 2028
Finish at recent pace
August 2038
Construction started
June 2025
First registered
June 2025
Developer
Rabdan Real Estate Development
Community
Majan
Units
445
Escrow bank
Arab Bank
Name in Arabic
ربدان جيتس
Project number
3587
Site inspections
4

Schedule

Between April 2026 and October 2026 the site added about 0.7 points a month. At that rate it would finish around August 2038, more than three months after its registered date of June 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

27 October 2026

5.2%+4.1 pts

  • Rabdan Gates construction site, inspection photo 1, 27 October 2026
  • Rabdan Gates construction site, inspection photo 2, 27 October 2026
  • Rabdan Gates construction site, inspection photo 3, 27 October 2026
  • Rabdan Gates construction site, inspection photo 4, 27 October 2026

23 April 2026

1.1%+1.1 pts

  • Rabdan Gates construction site, inspection photo 1, 23 April 2026
  • Rabdan Gates construction site, inspection photo 2, 23 April 2026
  • Rabdan Gates construction site, inspection photo 3, 23 April 2026
  • Rabdan Gates construction site, inspection photo 4, 23 April 2026

9 September 2025

0%

  • Rabdan Gates construction site, inspection photo 1, 9 September 2025
  • Rabdan Gates construction site, inspection photo 2, 9 September 2025

6 May 2025

0%

  • Rabdan Gates construction site, inspection photo 1, 6 May 2025
  • Rabdan Gates construction site, inspection photo 2, 6 May 2025

All 18 site photos, by inspection date

Context

Majan has 25 projects under construction, 28% built on average.

Rabdan Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Rabdan Gates?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Rabdan Gates handover date?
The registered completion date is June 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2038. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Rabdan Gates?
Rabdan Gates was 5.2% built at the site inspection on 27 October 2026. The site has been inspected 4 times since May 2025. The Land Department took 18 site photos at its inspections.
Is Rabdan Gates delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2028.
Who is building Rabdan Gates?
The registered developer is Rabdan Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Rabdan Gates?
Arab Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.