Gharbi II Residences construction progress

The registered completion date for Gharbi II Residences in Jumeirah Village Circle is July 2027. At the last site inspection, in November 2026, it was 21% built. The developer is Rabdan Real Estate Development.

21%

Built, at the site inspection of 16 November 2026

Running behind its date

Registered completion date
July 2027
Finish at recent pace
November 2030
Construction started
January 2025
First registered
February 2025
Developer
Rabdan Real Estate Development
Units
236
Escrow bank
Commercial Bank of Dubai
Name in Arabic
غربي Ii
Project number
3258
Site inspections
6

Schedule

Between March 2026 and November 2026 the site added about 1.7 points a month. At that rate it would finish around November 2030, more than three months after its registered date of July 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

16 November 2026

21%+6.1 pts

  • Gharbi II Residences construction site, inspection photo 1, 16 November 2026
  • Gharbi II Residences construction site, inspection photo 2, 16 November 2026
  • Gharbi II Residences construction site, inspection photo 3, 16 November 2026
  • Gharbi II Residences construction site, inspection photo 4, 16 November 2026

14 August 2026

14%+5.2 pts

  • Gharbi II Residences construction site, inspection photo 1, 14 August 2026
  • Gharbi II Residences construction site, inspection photo 2, 14 August 2026
  • Gharbi II Residences construction site, inspection photo 3, 14 August 2026
  • Gharbi II Residences construction site, inspection photo 4, 14 August 2026

14 May 2026

9.3%+2.2 pts

  • Gharbi II Residences construction site, inspection photo 1, 14 May 2026
  • Gharbi II Residences construction site, inspection photo 2, 14 May 2026
  • Gharbi II Residences construction site, inspection photo 3, 14 May 2026
  • Gharbi II Residences construction site, inspection photo 4, 14 May 2026

13 March 2026

7.1%+0.3 pts

  • Gharbi II Residences construction site, inspection photo 1, 13 March 2026
  • Gharbi II Residences construction site, inspection photo 2, 13 March 2026

29 April 2025

6.8%+6.8 pts

  • Gharbi II Residences construction site, inspection photo 1, 29 April 2025
  • Gharbi II Residences construction site, inspection photo 2, 29 April 2025
  • Gharbi II Residences construction site, inspection photo 3, 29 April 2025
  • Gharbi II Residences construction site, inspection photo 4, 29 April 2025

24 September 2024

0%

  • Gharbi II Residences construction site, inspection photo 1, 24 September 2024
  • Gharbi II Residences construction site, inspection photo 2, 24 September 2024

All 24 site photos, by inspection date

Context

Jumeirah Village Circle has 118 projects under construction, 42% built on average.

Rabdan Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Gharbi II Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Gharbi II Residences handover date?
The registered completion date is July 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Gharbi II Residences?
Gharbi II Residences was 21% built at the site inspection on 16 November 2026. The site has been inspected 6 times since September 2024. The Land Department took 24 site photos at its inspections.
Is Gharbi II Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2027.
Who is building Gharbi II Residences?
The registered developer is Rabdan Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Gharbi II Residences?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.