Gharbi Ii Residences construction progress

Gharbi Ii Residences in Jumeirah Village Circle is 14% built at the Land Department inspection of August 2026. Developer Rabdan Real Estate Development. Completion registered for July 2027.

14%

Built, at the Land Department site inspection of 14 August 2026

Running behind its date

Completion date (Land Department)
July 2027
Finish at recent pace
July 2031
Construction started
January 2025
Registered with the Land Department
February 2025
Developer
Rabdan Real Estate Development
Units
236
Escrow bank
Commercial Bank of Dubai
Name in Arabic
غربي Ii
Land Department project number
3258
Land Department site inspections
5

Schedule

Between March 2026 and August 2026 the site added about 1.5 points a month. At that rate it would finish around July 2031, more than three months after the July 2027 date registered with the Land Department.

0%25%50%75%100%202520262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

14 August 2026

14%+5.2 pts

  • Gharbi Ii Residences construction site, Land Department inspection photo 1, 14 August 2026
  • Gharbi Ii Residences construction site, Land Department inspection photo 2, 14 August 2026
  • Gharbi Ii Residences construction site, Land Department inspection photo 3, 14 August 2026
  • Gharbi Ii Residences construction site, Land Department inspection photo 4, 14 August 2026

14 May 2026

9.3%+2.2 pts

  • Gharbi Ii Residences construction site, Land Department inspection photo 1, 14 May 2026
  • Gharbi Ii Residences construction site, Land Department inspection photo 2, 14 May 2026
  • Gharbi Ii Residences construction site, Land Department inspection photo 3, 14 May 2026
  • Gharbi Ii Residences construction site, Land Department inspection photo 4, 14 May 2026

13 March 2026

7.1%+0.3 pts

  • Gharbi Ii Residences construction site, Land Department inspection photo 1, 13 March 2026
  • Gharbi Ii Residences construction site, Land Department inspection photo 2, 13 March 2026

29 April 2025

6.8%+6.8 pts

  • Gharbi Ii Residences construction site, Land Department inspection photo 1, 29 April 2025
  • Gharbi Ii Residences construction site, Land Department inspection photo 2, 29 April 2025
  • Gharbi Ii Residences construction site, Land Department inspection photo 3, 29 April 2025
  • Gharbi Ii Residences construction site, Land Department inspection photo 4, 29 April 2025

24 September 2024

0%

  • Gharbi Ii Residences construction site, Land Department inspection photo 1, 24 September 2024
  • Gharbi Ii Residences construction site, Land Department inspection photo 2, 24 September 2024

All 18 site photos, by inspection date

Context

Jumeirah Village Circle has 119 projects under construction, 40% built on average.

Rabdan Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Gharbi Ii Residences?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Gharbi Ii Residences be completed?
The completion date registered with the Dubai Land Department is July 2027. At the pace of its recent inspections the site would reach 100% around July 2031. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Gharbi Ii Residences is built?
14%, measured at the Land Department site inspection on 14 August 2026. The Land Department engineers have inspected the site 5 times since September 2024.
Is Gharbi Ii Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2027.
Who is building Gharbi Ii Residences?
The registered developer is Rabdan Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Gharbi Ii Residences?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.