Gharbi II Residences construction progress
The registered completion date for Gharbi II Residences in Jumeirah Village Circle is July 2027. At the last site inspection, in November 2026, it was 21% built. The developer is Rabdan Real Estate Development.
21%
Built, at the site inspection of 16 November 2026
Running behind its date
- Registered completion date
- July 2027
- Finish at recent pace
- November 2030
- Construction started
- January 2025
- First registered
- February 2025
- Developer
- Rabdan Real Estate Development
- Community
- Jumeirah Village Circle
- Units
- 236
- Escrow bank
- Commercial Bank of Dubai
- Name in Arabic
- غربي Ii
- Project number
- 3258
- Site inspections
- 6
Schedule
Between March 2026 and November 2026 the site added about 1.7 points a month. At that rate it would finish around November 2030, more than three months after its registered date of July 2027.
Site inspections
16 November 2026
21%+6.1 pts
14 August 2026
14%+5.2 pts
14 May 2026
9.3%+2.2 pts
13 March 2026
7.1%+0.3 pts
29 April 2025
6.8%+6.8 pts
24 September 2024
0%
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
Rabdan Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Gharbi II Residences?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Gharbi II Residences handover date?
- The registered completion date is July 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Gharbi II Residences?
- Gharbi II Residences was 21% built at the site inspection on 16 November 2026. The site has been inspected 6 times since September 2024. The Land Department took 24 site photos at its inspections.
- Is Gharbi II Residences delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of July 2027.
- Who is building Gharbi II Residences?
- The registered developer is Rabdan Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Gharbi II Residences?
- Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Rabdan GatesAlso by Rabdan Real Estate Development. 5.2%, Due June 2028.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.








.jpeg&w=3840&q=75)