Divine Al Barari construction progress
The registered completion date for Divine Al Barari in Majan is March 2028. At the last site inspection, in October 2026, it was 20% built. The developer is Takmeel Real Estate Development.
20%
Built, at the site inspection of 20 October 2026
Running behind its date
- Registered completion date
- March 2028
- Finish at recent pace
- December 2030
- Construction started
- November 2025
- First registered
- September 2025
- Developer
- Takmeel Real Estate Development
- Community
- Majan
- Units
- 291
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- ديفاين البراري
- Project number
- 3759
- Site inspections
- 3
Schedule
Between May 2026 and October 2026 the site added about 1.6 points a month. At that rate it would finish around December 2030, more than three months after its registered date of March 2028.
Site inspections
20 October 2026
20%+8.0 pts
19 May 2026
12%+12 pts
21 May 2025
0%
Context
Majan has 25 projects under construction, 28% built on average.
Takmeel Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Divine Al Barari?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Divine Al Barari handover date?
- The registered completion date is March 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Divine Al Barari?
- Divine Al Barari was 20% built at the site inspection on 20 October 2026. The site has been inspected 3 times since May 2025. The Land Department took 14 site photos at its inspections.
- Is Divine Al Barari delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
- Who is building Divine Al Barari?
- The registered developer is Takmeel Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Divine Al Barari?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Divine ElementsAlso by Takmeel Real Estate Development. 0%, Due December 2027.
- Sherena Residence 2Nearby in Majan. 82%, Due August 2022, passed.
- Samana Barari ViewsNearby in Majan. 32%, Due March 2027.
- Samana Barari Views 2Nearby in Majan. 26%.
- Barari Parkview By Al MawaredNearby in Majan. 45%, Due December 2027.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.