Divine Elements construction progress
The registered completion date for Divine Elements is December 2027. At the last site inspection, in July 2026, it was 0% built. The developer is Takmeel Real Estate Development.
0%
Built, at the site inspection of 8 July 2026
Running behind its date
- Registered completion date
- December 2027
- Finish at recent pace
- August 3839
- Construction started
- January 2026
- First registered
- November 2025
- Developer
- Takmeel Real Estate Development
- Units
- 90
- Escrow bank
- United Bank Limited
- Name in Arabic
- ديفاين اليمنتس
- Project number
- 4142
- Site inspections
- 2
Schedule
Between October 2025 and July 2026 the site added about 0.0 points a month. At that rate it would finish around August 3839, more than three months after its registered date of December 2027.
Site inspections
8 July 2026
0%+0.0 pts
16 October 2025
0%
Context
Takmeel Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Divine Elements?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Divine Elements handover date?
- The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 3839. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Divine Elements?
- Divine Elements was 0% built at the site inspection on 8 July 2026. The site has been inspected 2 times since October 2025. The Land Department took 5 site photos at its inspections.
- Is Divine Elements delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
- Who is building Divine Elements?
- The registered developer is Takmeel Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Divine Elements?
- United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Divine Al BarariAlso by Takmeel Real Estate Development. 20%, Due March 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.