Barari Views construction progress

The register lists Barari Views in Majan as complete, with a registered completion date of March 2024. Its last site inspection on record was in October 2025. The developer is P C I Real Estate Developers.

100%

Built, at the site inspection of 24 October 2025

Construction complete

Registered completion date
March 2024
Construction started
March 2022
First registered
January 2023
Community
Majan
Units
26
Escrow bank
United Bank Limited
Name in Arabic
براري فيوس
Project number
2500
Site inspections
10

Schedule

The register lists Barari Views as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%202320242025
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

24 October 2025

100%+1.1 pts

  • Barari Views construction site, inspection photo 1, 24 October 2025
  • Barari Views construction site, inspection photo 2, 24 October 2025
  • Barari Views construction site, inspection photo 3, 24 October 2025
  • Barari Views construction site, inspection photo 4, 24 October 2025

16 July 2025

99%+1.4 pts

  • Barari Views construction site, inspection photo 1, 16 July 2025
  • Barari Views construction site, inspection photo 2, 16 July 2025
  • Barari Views construction site, inspection photo 3, 16 July 2025
  • Barari Views construction site, inspection photo 4, 16 July 2025

27 March 2025

97%+9.9 pts

  • Barari Views construction site, inspection photo 1, 27 March 2025
  • Barari Views construction site, inspection photo 2, 27 March 2025
  • Barari Views construction site, inspection photo 3, 27 March 2025
  • Barari Views construction site, inspection photo 4, 27 March 2025

19 November 2024

88%+14 pts

  • Barari Views construction site, inspection photo 1, 19 November 2024
  • Barari Views construction site, inspection photo 2, 19 November 2024
  • Barari Views construction site, inspection photo 3, 19 November 2024
  • Barari Views construction site, inspection photo 4, 19 November 2024

9 July 2024

74%+6.0 pts

  • Barari Views construction site, inspection photo 1, 9 July 2024
  • Barari Views construction site, inspection photo 2, 9 July 2024
  • Barari Views construction site, inspection photo 3, 9 July 2024
  • Barari Views construction site, inspection photo 4, 9 July 2024

25 March 2024

68%+18 pts

  • Barari Views construction site, inspection photo 1, 25 March 2024
  • Barari Views construction site, inspection photo 2, 25 March 2024
  • Barari Views construction site, inspection photo 3, 25 March 2024
  • Barari Views construction site, inspection photo 4, 25 March 2024

22 November 2023

50%+2.9 pts

  • Barari Views construction site, inspection photo 1, 22 November 2023
  • Barari Views construction site, inspection photo 2, 22 November 2023
  • Barari Views construction site, inspection photo 3, 22 November 2023
  • Barari Views construction site, inspection photo 4, 22 November 2023

16 October 2023

47%+4.6 pts

  • Barari Views construction site, inspection photo 1, 16 October 2023
  • Barari Views construction site, inspection photo 2, 16 October 2023
  • Barari Views construction site, inspection photo 3, 16 October 2023
  • Barari Views construction site, inspection photo 4, 16 October 2023

5 June 2023

42%+17 pts

  • Barari Views construction site, inspection photo 1, 5 June 2023
  • Barari Views construction site, inspection photo 2, 5 June 2023
  • Barari Views construction site, inspection photo 3, 5 June 2023
  • Barari Views construction site, inspection photo 4, 5 June 2023

21 November 2022

26%

  • Barari Views construction site, inspection photo 1, 21 November 2022
  • Barari Views construction site, inspection photo 2, 21 November 2022
  • Barari Views construction site, inspection photo 3, 21 November 2022
  • Barari Views construction site, inspection photo 4, 21 November 2022

All 95 site photos, by inspection date

Context

Majan has 25 projects under construction, 28% built on average.

P C I Real Estate Developers has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Barari Views?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Barari Views handover date?
Construction of Barari Views is recorded as complete, with a registered completion date of March 2024. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Barari Views?
Barari Views was 100% built at the site inspection on 24 October 2025. The site has been inspected 10 times since November 2022. The Land Department took 95 site photos at its inspections.
Is Barari Views delayed?
The register lists construction as complete.
Who is building Barari Views?
The registered developer is P C I Real Estate Developers. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Barari Views?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.