Gateway By Premier Choice construction progress
No completion date is registered for Gateway By Premier Choice in Jumeirah Village Circle yet. At the last site inspection, in September 2026, it was 68% built. The developer is P C I Real Estate Developers.
68%
Built, at the site inspection of 22 September 2026
- Finish at recent pace
- January 2029
- Construction started
- August 2023
- First registered
- July 2023
- Developer
- P C I Real Estate Developers
- Community
- Jumeirah Village Circle
- Units
- 152
- Escrow bank
- United Bank Limited
- Name in Arabic
- واسطة اختيار بريميير بوابة
- Project number
- 2688
- Site inspections
- 12
Schedule
Since November 2025 Gateway By Premier Choice has added about 1.2 points a month. At that rate the site reaches 100% around January 2029. No completion date is on record to compare it with.
Site inspections
22 September 2026
68%+0.6 pts
19 June 2026
67%+0.4 pts
26 February 2026
67%+10 pts
26 November 2025
57%+4.4 pts
25 August 2025
52%+7.3 pts
19 May 2025
45%+9.3 pts
24 February 2025
36%+13 pts
27 November 2024
23%+9.9 pts
19 August 2024
13%+11 pts
4 May 2024
1.4%+0.0 pts
Context
Jumeirah Village Circle has 118 projects under construction, 42% built on average.
P C I Real Estate Developers has 2 projects under construction in Dubai, none past their registered completion dates.
Own a unit in Gateway By Premier Choice?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Gateway By Premier Choice handover date?
- No completion date is on record for Gateway By Premier Choice yet. Handover follows completion, so there is no date to give.
- What is the latest construction update on Gateway By Premier Choice?
- Gateway By Premier Choice was 68% built at the site inspection on 22 September 2026. The site has been inspected 12 times since June 2023. The Land Department took 83 site photos at its inspections.
- Who is building Gateway By Premier Choice?
- The registered developer is P C I Real Estate Developers. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Gateway By Premier Choice?
- United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- South Lofts By Premier ChoiceAlso by P C I Real Estate Developers. 0%, Due January 2029.
- German Supreme Tower 2Nearby in Jumeirah Village Circle. 45%, Due January 2029.
- Aliva GreenNearby in Jumeirah Village Circle. 52%, Due November 2025, passed.
- Dusit Princess RijasNearby in Jumeirah Village Circle. 64%, Due April 2027.
- Samana WavesNearby in Jumeirah Village Circle. 91%, Due April 2026, passed.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.









.jpeg&w=3840&q=75)