The Wilds 2 construction progress

The registered completion date for The Wilds 2 in Living Legends is February 2029. At the last site inspection, in September 2026, it was 5.7% built. The developer is Aurora Spv 2.

5.7%

Built, at the site inspection of 14 September 2026

Running behind its date

Registered completion date
February 2029
Finish at recent pace
December 2040
Construction started
April 2025
First registered
May 2025
Developer
Aurora Spv 2
Units
266
Escrow bank
First Abu Dhabi Bank
Name in Arabic
ذا وايلدز 2
Project number
3606
Site inspections
4

Schedule

Between February 2026 and September 2026 the site added about 0.6 points a month. At that rate it would finish around December 2040, more than three months after its registered date of February 2029.

0%25%50%75%100%2026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 September 2026

5.7%+3.0 pts

  • The Wilds 2 construction site, inspection photo 1, 14 September 2026
  • The Wilds 2 construction site, inspection photo 2, 14 September 2026
  • The Wilds 2 construction site, inspection photo 3, 14 September 2026
  • The Wilds 2 construction site, inspection photo 4, 14 September 2026

16 June 2026

2.7%+0.6 pts

  • The Wilds 2 construction site, inspection photo 1, 16 June 2026
  • The Wilds 2 construction site, inspection photo 2, 16 June 2026
  • The Wilds 2 construction site, inspection photo 3, 16 June 2026

25 February 2026

2.1%+2.1 pts

  • The Wilds 2 construction site, inspection photo 1, 25 February 2026
  • The Wilds 2 construction site, inspection photo 2, 25 February 2026
  • The Wilds 2 construction site, inspection photo 3, 25 February 2026
  • The Wilds 2 construction site, inspection photo 4, 25 February 2026

21 March 2025

0%

  • The Wilds 2 construction site, inspection photo 1, 21 March 2025
  • The Wilds 2 construction site, inspection photo 2, 21 March 2025

All 18 site photos, by inspection date

Context

Living Legends has 6 projects under construction, 49% built on average.

Aurora Spv 2 has 4 projects under construction in Dubai, none past their registered completion dates.

Own a unit in The Wilds 2?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Wilds 2 handover date?
The registered completion date is February 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2040. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Wilds 2?
The Wilds 2 was 5.7% built at the site inspection on 14 September 2026. The site has been inspected 4 times since March 2025. The Land Department took 18 site photos at its inspections.
Is The Wilds 2 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2029.
Who is building The Wilds 2?
The registered developer is Aurora Spv 2. It has 3 other projects under construction in Dubai.
Which bank holds the escrow account for The Wilds 2?
First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.