Living Legends Phase 6 construction progress
Living Legends Phase 6 in Living Legends is 77% built at the Land Department inspection of June 2026. Developer Dawn Real Estate Development. Completion registered for July 2026.
77%
Built, at the Land Department site inspection of 17 June 2026
3 months past its registered completion date
- Completion date (Land Department)
- July 2026
- Finish at recent pace
- August 2028
- Construction started
- August 2023
- Registered with the Land Department
- August 2023
- Developer
- Dawn Real Estate Development
- Community
- Living Legends
- Units
- 652
- Escrow bank
- Sharjah Islamic Bank
- Name in Arabic
- الأساطير الحية المرحلة 6
- Land Department project number
- 1325
- Land Department site inspections
- 23
Schedule
Living Legends Phase 6 was registered to complete in July 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 0.9 points a month. Kept at that rate, the site would reach 100% around August 2028.
Site inspections
17 June 2026
77%+1.6 pts
24 March 2026
75%+5.9 pts
3 October 2025
69%+1.9 pts
19 May 2025
67%+3.6 pts
5 February 2025
64%+3.5 pts
12 September 2024
60%+17 pts
21 May 2024
43%+0.9 pts
5 December 2023
43%+0.0 pts
27 January 2022
43%+0.2 pts
24 May 2021
42%+0.5 pts
Context
Living Legends has 6 projects under construction, 49% built on average.
Own a unit in Living Legends Phase 6?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Living Legends Phase 6 be completed?
- The completion date registered with the Dubai Land Department is July 2026. At the pace of its recent inspections the site would reach 100% around August 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Living Legends Phase 6 is built?
- 77%, measured at the Land Department site inspection on 17 June 2026. The Land Department engineers have inspected the site 23 times since November 2012.
- Is Living Legends Phase 6 delayed?
- Yes. Its registered completion date of July 2026 has passed and the Land Department still lists it as under construction.
- Who is building Living Legends Phase 6?
- The registered developer is Dawn Real Estate Development.
- Which bank holds the escrow account for Living Legends Phase 6?
- Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Living Legends Phase 4Nearby in Living Legends. 62%, Due March 2027.
- Living Legends Phase 5Nearby in Living Legends. 49%, Due March 2025, passed.
- Living Legends Phase 7Nearby in Living Legends. 92%, Due September 2021, passed.
- The Wilds 1Nearby in Living Legends. 7.5%, Due January 2029.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)




















.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)
.jpg&w=3840&q=75)