Living Legends Phase 6 construction progress

Living Legends Phase 6 in Living Legends is 77% built at the Land Department inspection of June 2026. Developer Dawn Real Estate Development. Completion registered for July 2026.

77%

Built, at the Land Department site inspection of 17 June 2026

3 months past its registered completion date

Completion date (Land Department)
July 2026
Finish at recent pace
August 2028
Construction started
August 2023
Registered with the Land Department
August 2023
Developer
Dawn Real Estate Development
Units
652
Escrow bank
Sharjah Islamic Bank
Name in Arabic
الأساطير الحية المرحلة 6
Land Department project number
1325
Land Department site inspections
23

Schedule

Living Legends Phase 6 was registered to complete in July 2026, 3 months ago, and is still under construction. Over the last year of inspections it has added about 0.9 points a month. Kept at that rate, the site would reach 100% around August 2028.

0%25%50%75%100%20132016201920222025
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

17 June 2026

77%+1.6 pts

  • Living Legends Phase 6 construction site, Land Department inspection photo 1, 17 June 2026
  • Living Legends Phase 6 construction site, Land Department inspection photo 2, 17 June 2026
  • Living Legends Phase 6 construction site, Land Department inspection photo 3, 17 June 2026
  • Living Legends Phase 6 construction site, Land Department inspection photo 4, 17 June 2026

24 March 2026

75%+5.9 pts

  • Living Legends Phase 6 construction site, Land Department inspection photo 1, 24 March 2026
  • Living Legends Phase 6 construction site, Land Department inspection photo 2, 24 March 2026
  • Living Legends Phase 6 construction site, Land Department inspection photo 3, 24 March 2026
  • Living Legends Phase 6 construction site, Land Department inspection photo 4, 24 March 2026

3 October 2025

69%+1.9 pts

  • Living Legends Phase 6 construction site, Land Department inspection photo 1, 3 October 2025
  • Living Legends Phase 6 construction site, Land Department inspection photo 2, 3 October 2025
  • Living Legends Phase 6 construction site, Land Department inspection photo 3, 3 October 2025
  • Living Legends Phase 6 construction site, Land Department inspection photo 4, 3 October 2025

19 May 2025

67%+3.6 pts

  • Living Legends Phase 6 construction site, Land Department inspection photo 1, 19 May 2025
  • Living Legends Phase 6 construction site, Land Department inspection photo 2, 19 May 2025
  • Living Legends Phase 6 construction site, Land Department inspection photo 3, 19 May 2025
  • Living Legends Phase 6 construction site, Land Department inspection photo 4, 19 May 2025

5 February 2025

64%+3.5 pts

  • Living Legends Phase 6 construction site, Land Department inspection photo 1, 5 February 2025
  • Living Legends Phase 6 construction site, Land Department inspection photo 2, 5 February 2025
  • Living Legends Phase 6 construction site, Land Department inspection photo 3, 5 February 2025
  • Living Legends Phase 6 construction site, Land Department inspection photo 4, 5 February 2025

12 September 2024

60%+17 pts

  • Living Legends Phase 6 construction site, Land Department inspection photo 1, 12 September 2024
  • Living Legends Phase 6 construction site, Land Department inspection photo 2, 12 September 2024
  • Living Legends Phase 6 construction site, Land Department inspection photo 3, 12 September 2024
  • Living Legends Phase 6 construction site, Land Department inspection photo 4, 12 September 2024

21 May 2024

43%+0.9 pts

  • Living Legends Phase 6 construction site, Land Department inspection photo 1, 21 May 2024
  • Living Legends Phase 6 construction site, Land Department inspection photo 2, 21 May 2024
  • Living Legends Phase 6 construction site, Land Department inspection photo 3, 21 May 2024
  • Living Legends Phase 6 construction site, Land Department inspection photo 4, 21 May 2024

5 December 2023

43%+0.0 pts

  • Living Legends Phase 6 construction site, Land Department inspection photo 1, 5 December 2023
  • Living Legends Phase 6 construction site, Land Department inspection photo 2, 5 December 2023
  • Living Legends Phase 6 construction site, Land Department inspection photo 3, 5 December 2023
  • Living Legends Phase 6 construction site, Land Department inspection photo 4, 5 December 2023

27 January 2022

43%+0.2 pts

  • Living Legends Phase 6 construction site, Land Department inspection photo 1, 27 January 2022
  • Living Legends Phase 6 construction site, Land Department inspection photo 2, 27 January 2022
  • Living Legends Phase 6 construction site, Land Department inspection photo 3, 27 January 2022
  • Living Legends Phase 6 construction site, Land Department inspection photo 4, 27 January 2022

24 May 2021

42%+0.5 pts

  • Living Legends Phase 6 construction site, Land Department inspection photo 1, 24 May 2021
  • Living Legends Phase 6 construction site, Land Department inspection photo 2, 24 May 2021
  • Living Legends Phase 6 construction site, Land Department inspection photo 3, 24 May 2021
  • Living Legends Phase 6 construction site, Land Department inspection photo 4, 24 May 2021

All 183 site photos, by inspection date

Context

Living Legends has 6 projects under construction, 49% built on average.

Own a unit in Living Legends Phase 6?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Living Legends Phase 6 be completed?
The completion date registered with the Dubai Land Department is July 2026. At the pace of its recent inspections the site would reach 100% around August 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Living Legends Phase 6 is built?
77%, measured at the Land Department site inspection on 17 June 2026. The Land Department engineers have inspected the site 23 times since November 2012.
Is Living Legends Phase 6 delayed?
Yes. Its registered completion date of July 2026 has passed and the Land Department still lists it as under construction.
Who is building Living Legends Phase 6?
The registered developer is Dawn Real Estate Development.
Which bank holds the escrow account for Living Legends Phase 6?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.