Living Legends Phase 4 construction progress

Living Legends Phase 4 in Living Legends is 62% built at the Land Department inspection of March 2026. Developer Amer Alghurair Real Estate Development Co. Completion registered for March 2027.

62%

Built, at the Land Department site inspection of 13 March 2026

On pace for its date

Completion date (Land Department)
March 2027
Finish at recent pace
May 2027
Construction started
June 2024
Registered with the Land Department
June 2024
Developer
Amer Alghurair Real Estate Development Co
Units
555
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
الأساطير الحية المرحلة 4
Land Department project number
1323
Land Department site inspections
18

Schedule

Since July 2025 Living Legends Phase 4 has added about 2.8 points a month. That puts 100% around May 2027, within three months of its registered completion date of March 2027.

0%25%50%75%100%20132016201920222025
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

13 March 2026

62%+22 pts

  • Living Legends Phase 4 construction site, Land Department inspection photo 1, 13 March 2026
  • Living Legends Phase 4 construction site, Land Department inspection photo 2, 13 March 2026
  • Living Legends Phase 4 construction site, Land Department inspection photo 3, 13 March 2026
  • Living Legends Phase 4 construction site, Land Department inspection photo 4, 13 March 2026

15 July 2025

40%+7.3 pts

  • Living Legends Phase 4 construction site, Land Department inspection photo 1, 15 July 2025
  • Living Legends Phase 4 construction site, Land Department inspection photo 2, 15 July 2025
  • Living Legends Phase 4 construction site, Land Department inspection photo 3, 15 July 2025
  • Living Legends Phase 4 construction site, Land Department inspection photo 4, 15 July 2025

5 December 2024

33%+2.2 pts

  • Living Legends Phase 4 construction site, Land Department inspection photo 1, 5 December 2024
  • Living Legends Phase 4 construction site, Land Department inspection photo 2, 5 December 2024
  • Living Legends Phase 4 construction site, Land Department inspection photo 3, 5 December 2024
  • Living Legends Phase 4 construction site, Land Department inspection photo 4, 5 December 2024

31 October 2024

31%+2.4 pts

  • Living Legends Phase 4 construction site, Land Department inspection photo 1, 31 October 2024
  • Living Legends Phase 4 construction site, Land Department inspection photo 2, 31 October 2024
  • Living Legends Phase 4 construction site, Land Department inspection photo 3, 31 October 2024
  • Living Legends Phase 4 construction site, Land Department inspection photo 4, 31 October 2024

28 April 2021

28%

  • Living Legends Phase 4 construction site, Land Department inspection photo 1, 28 April 2021
  • Living Legends Phase 4 construction site, Land Department inspection photo 2, 28 April 2021
  • Living Legends Phase 4 construction site, Land Department inspection photo 3, 28 April 2021
  • Living Legends Phase 4 construction site, Land Department inspection photo 4, 28 April 2021

28 May 2020

28%

  • Living Legends Phase 4 construction site, Land Department inspection photo 1, 28 May 2020
  • Living Legends Phase 4 construction site, Land Department inspection photo 2, 28 May 2020
  • Living Legends Phase 4 construction site, Land Department inspection photo 3, 28 May 2020
  • Living Legends Phase 4 construction site, Land Department inspection photo 4, 28 May 2020

23 July 2019

28%

  • Living Legends Phase 4 construction site, Land Department inspection photo 1, 23 July 2019
  • Living Legends Phase 4 construction site, Land Department inspection photo 2, 23 July 2019
  • Living Legends Phase 4 construction site, Land Department inspection photo 3, 23 July 2019
  • Living Legends Phase 4 construction site, Land Department inspection photo 4, 23 July 2019

10 March 2019

30%

  • Living Legends Phase 4 construction site, Land Department inspection photo 1, 10 March 2019
  • Living Legends Phase 4 construction site, Land Department inspection photo 2, 10 March 2019
  • Living Legends Phase 4 construction site, Land Department inspection photo 3, 10 March 2019
  • Living Legends Phase 4 construction site, Land Department inspection photo 4, 10 March 2019

8 May 2018

30%+0.5 pts

  • Living Legends Phase 4 construction site, Land Department inspection photo 1, 8 May 2018
  • Living Legends Phase 4 construction site, Land Department inspection photo 2, 8 May 2018
  • Living Legends Phase 4 construction site, Land Department inspection photo 3, 8 May 2018
  • Living Legends Phase 4 construction site, Land Department inspection photo 4, 8 May 2018

14 February 2017

29%+5.2 pts

  • Living Legends Phase 4 construction site, Land Department inspection photo 1, 14 February 2017
  • Living Legends Phase 4 construction site, Land Department inspection photo 2, 14 February 2017
  • Living Legends Phase 4 construction site, Land Department inspection photo 3, 14 February 2017
  • Living Legends Phase 4 construction site, Land Department inspection photo 4, 14 February 2017

All 115 site photos, by inspection date

Context

Living Legends has 6 projects under construction, 49% built on average. Living Legends Phase 4 is ahead of that average.

Amer Alghurair Real Estate Development Co has 2 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Living Legends Phase 4?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Living Legends Phase 4 be completed?
The completion date registered with the Dubai Land Department is March 2027. At the pace of its recent inspections the site would reach 100% around May 2027. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Living Legends Phase 4 is built?
62%, measured at the Land Department site inspection on 13 March 2026. The Land Department engineers have inspected the site 18 times since November 2012.
Is Living Legends Phase 4 delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of March 2027.
Who is building Living Legends Phase 4?
The registered developer is Amer Alghurair Real Estate Development Co. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Living Legends Phase 4?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.