Living Legends Phase 5 construction progress

Living Legends Phase 5 in Living Legends is 49% built at the Land Department inspection of April 2026. Developer Amer Alghurair Real Estate Development Co. Completion registered for March 2025.

49%

Built, at the Land Department site inspection of 13 April 2026

18 months past its registered completion date

Completion date (Land Department)
March 2025
Finish at recent pace
January 2570
Construction started
January 2024
Registered with the Land Department
January 2024
Developer
Amer Alghurair Real Estate Development Co
Units
928
Escrow bank
Abu Dhabi Islamic Bank
Name in Arabic
الأساطير الحية المرحلة 5
Land Department project number
1324
Land Department site inspections
15

Schedule

Living Legends Phase 5 was registered to complete in March 2025, 18 months ago, and is still under construction. Over the last year of inspections it has added about 0.0 points a month. Kept at that rate, the site would reach 100% around January 2570.

0%25%50%75%100%20132016201920222025
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

13 April 2026

49%+0.1 pts

  • Living Legends Phase 5 construction site, Land Department inspection photo 1, 13 April 2026
  • Living Legends Phase 5 construction site, Land Department inspection photo 2, 13 April 2026
  • Living Legends Phase 5 construction site, Land Department inspection photo 3, 13 April 2026
  • Living Legends Phase 5 construction site, Land Department inspection photo 4, 13 April 2026

15 July 2025

49%+8.8 pts

  • Living Legends Phase 5 construction site, Land Department inspection photo 1, 15 July 2025
  • Living Legends Phase 5 construction site, Land Department inspection photo 2, 15 July 2025
  • Living Legends Phase 5 construction site, Land Department inspection photo 3, 15 July 2025
  • Living Legends Phase 5 construction site, Land Department inspection photo 4, 15 July 2025

5 December 2024

40%+5.0 pts

  • Living Legends Phase 5 construction site, Land Department inspection photo 1, 5 December 2024
  • Living Legends Phase 5 construction site, Land Department inspection photo 2, 5 December 2024
  • Living Legends Phase 5 construction site, Land Department inspection photo 3, 5 December 2024
  • Living Legends Phase 5 construction site, Land Department inspection photo 4, 5 December 2024

13 August 2024

35%+9.3 pts

  • Living Legends Phase 5 construction site, Land Department inspection photo 1, 13 August 2024
  • Living Legends Phase 5 construction site, Land Department inspection photo 2, 13 August 2024
  • Living Legends Phase 5 construction site, Land Department inspection photo 3, 13 August 2024
  • Living Legends Phase 5 construction site, Land Department inspection photo 4, 13 August 2024

28 April 2021

26%

  • Living Legends Phase 5 construction site, Land Department inspection photo 1, 28 April 2021
  • Living Legends Phase 5 construction site, Land Department inspection photo 2, 28 April 2021
  • Living Legends Phase 5 construction site, Land Department inspection photo 3, 28 April 2021
  • Living Legends Phase 5 construction site, Land Department inspection photo 4, 28 April 2021

17 February 2020

26%

  • Living Legends Phase 5 construction site, Land Department inspection photo 1, 17 February 2020
  • Living Legends Phase 5 construction site, Land Department inspection photo 2, 17 February 2020
  • Living Legends Phase 5 construction site, Land Department inspection photo 3, 17 February 2020
  • Living Legends Phase 5 construction site, Land Department inspection photo 4, 17 February 2020

10 March 2019

27%

  • Living Legends Phase 5 construction site, Land Department inspection photo 1, 10 March 2019
  • Living Legends Phase 5 construction site, Land Department inspection photo 2, 10 March 2019
  • Living Legends Phase 5 construction site, Land Department inspection photo 3, 10 March 2019
  • Living Legends Phase 5 construction site, Land Department inspection photo 4, 10 March 2019

14 February 2017

27%+1.5 pts

  • Living Legends Phase 5 construction site, Land Department inspection photo 1, 14 February 2017
  • Living Legends Phase 5 construction site, Land Department inspection photo 2, 14 February 2017
  • Living Legends Phase 5 construction site, Land Department inspection photo 3, 14 February 2017
  • Living Legends Phase 5 construction site, Land Department inspection photo 4, 14 February 2017

12 April 2016

25%+0.9 pts

  • Living Legends Phase 5 construction site, Land Department inspection photo 1, 12 April 2016
  • Living Legends Phase 5 construction site, Land Department inspection photo 2, 12 April 2016
  • Living Legends Phase 5 construction site, Land Department inspection photo 3, 12 April 2016
  • Living Legends Phase 5 construction site, Land Department inspection photo 4, 12 April 2016

24 June 2015

24%+2.5 pts

  • Living Legends Phase 5 construction site, Land Department inspection photo 1, 24 June 2015
  • Living Legends Phase 5 construction site, Land Department inspection photo 2, 24 June 2015
  • Living Legends Phase 5 construction site, Land Department inspection photo 3, 24 June 2015

All 92 site photos, by inspection date

Context

Living Legends has 6 projects under construction, 49% built on average. Living Legends Phase 5 is ahead of that average.

Amer Alghurair Real Estate Development Co has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Living Legends Phase 5?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Living Legends Phase 5 be completed?
The completion date registered with the Dubai Land Department is March 2025. At the pace of its recent inspections the site would reach 100% around January 2570. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Living Legends Phase 5 is built?
49%, measured at the Land Department site inspection on 13 April 2026. The Land Department engineers have inspected the site 15 times since November 2012.
Is Living Legends Phase 5 delayed?
Yes. Its registered completion date of March 2025 has passed and the Land Department still lists it as under construction.
Who is building Living Legends Phase 5?
The registered developer is Amer Alghurair Real Estate Development Co. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Living Legends Phase 5?
Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.