Golden Wood Views construction progress

The register lists Golden Wood Views in Jumeirah Village Triangle as complete, with a registered completion date of June 2020. Its last site inspection on record was in June 2020. The developer is Golden Wood Real Estate Development.

100%

Built, at the site inspection of 11 June 2020

Construction complete

Registered completion date
June 2020
Construction started
March 2017
First registered
March 2018
Units
60
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
غولدن وود فيوس
Project number
2021
Site inspections
2

Schedule

The register lists Golden Wood Views as 100% built. Handover of individual units follows on the developer's schedule, which it does not show.

0%25%50%75%100%201820192020
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

11 June 2020

100%+50 pts

  • Golden Wood Views construction site, inspection photo 1, 11 June 2020
  • Golden Wood Views construction site, inspection photo 2, 11 June 2020
  • Golden Wood Views construction site, inspection photo 3, 11 June 2020
  • Golden Wood Views construction site, inspection photo 4, 11 June 2020

4 February 2018

50%

  • Golden Wood Views construction site, inspection photo 1, 4 February 2018
  • Golden Wood Views construction site, inspection photo 2, 4 February 2018
  • Golden Wood Views construction site, inspection photo 3, 4 February 2018
  • Golden Wood Views construction site, inspection photo 4, 4 February 2018

All 26 site photos, by inspection date

Context

Jumeirah Village Triangle has 29 projects under construction, 27% built on average.

Golden Wood Real Estate Development has 2 projects under construction in Dubai; 2 have passed their registered completion date.

Own a unit in Golden Wood Views?

The building is finished, so now come the snagging, the handover papers, finding a tenant and keeping an eye on what the unit is worth. Mulki keeps all of that in one private app.

Notify me when it launches

Questions

When is the Golden Wood Views handover date?
Construction of Golden Wood Views is recorded as complete, with a registered completion date of June 2020. Handover of individual units follows on the developer's schedule, which the register does not show.
What is the latest construction update on Golden Wood Views?
Golden Wood Views was 100% built at the site inspection on 11 June 2020. The site has been inspected 2 times since February 2018. The Land Department took 26 site photos at its inspections.
Is Golden Wood Views delayed?
The register lists construction as complete.
Who is building Golden Wood Views?
The registered developer is Golden Wood Real Estate Development. It has 2 other projects under construction in Dubai.
Which bank holds the escrow account for Golden Wood Views?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.