Essenlife Residence construction progress
Essenlife Residence in Jumeirah Village Triangle is 7.2% built at the Land Department inspection of September 2026. Developer Object One Real Estate Development. Completion registered for March 2028.
7.2%
Built, at the Land Department site inspection of 16 September 2026
Running behind its date
- Completion date (Land Department)
- March 2028
- Finish at recent pace
- October 2040
- Construction started
- May 2025
- Registered with the Land Department
- May 2025
- Developer
- Object One Real Estate Development
- Community
- Jumeirah Village Triangle
- Units
- 357
- Escrow bank
- Abu Dhabi Islamic Bank
- Name in Arabic
- أس ان لايف ريزيدنس
- Land Department project number
- 3639
- Land Department site inspections
- 6
Schedule
Between November 2025 and September 2026 the site added about 0.5 points a month. At that rate it would finish around October 2040, more than three months after the March 2028 date registered with the Land Department.
Site inspections
16 September 2026
7.2%+1.1 pts
4 June 2026
6.1%+3.0 pts
17 February 2026
3.1%
16 February 2026
3.1%+1.3 pts
20 November 2025
1.8%+1.8 pts
24 April 2025
0%
Context
Jumeirah Village Triangle has 31 projects under construction, 28% built on average. Essenlife Residence is behind that average.
Object One Real Estate Development has 13 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Essenlife Residence?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Essenlife Residence be completed?
- The completion date registered with the Dubai Land Department is March 2028. At the pace of its recent inspections the site would reach 100% around October 2040. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Essenlife Residence is built?
- 7.2%, measured at the Land Department site inspection on 16 September 2026. The Land Department engineers have inspected the site 6 times since April 2025.
- Is Essenlife Residence delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
- Who is building Essenlife Residence?
- The registered developer is Object One Real Estate Development. It has 12 other projects under construction in Dubai.
- Which bank holds the escrow account for Essenlife Residence?
- Abu Dhabi Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- 1wood ResidenceAlso by Object One Real Estate Development. 94%.
- Ozone 1 ResidenceAlso by Object One Real Estate Development. 57%.
- Winner TowerAlso by Object One Real Estate Development. 28%.
- The Fifth TowerAlso by Object One Real Estate Development. 50%, Due July 2026, passed.
- Paradise OneNearby in Jumeirah Village Triangle. 70%, Due April 2027.
- Silver StallionsNearby in Jumeirah Village Triangle. 12%, Due December 2017, passed.
- Altai TowerNearby in Jumeirah Village Triangle. 98%, Due January 2026, passed.
- Fashionz 1 By DanubeNearby in Jumeirah Village Triangle. 40%.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.



.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)


.jpeg&w=3840&q=75)